16850 W BALLINGER ST 91343

Certificate Information: 16850 W BALLINGER ST 91343

Application / Permit
20014-20000-03167
Plan Check / Job No.
B20VN09812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 7'-7" x 7'-2" ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 SARKIS HARABEDIAN
Corrections Issued 8/4/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 9/23/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 1/6/2021 SARKIS HARABEDIAN
Plan Check Approved 2/10/2021 SARKIS HARABEDIAN
Issued 3/18/2021 APPLICANT
CofO in Progress 9/15/2021 MICHAEL TEMPLE
Permit Finaled 9/25/2021 MICHAEL SMITH
CofO Issued 9/25/2021 MICHAEL SMITH
Permit Finaled 9/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/23/2020 SARKIS HARABEDIAN
Address approval Cleared 10/21/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/1/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 12/1/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/1/2020 ABDULLAH SADOZAI
Construction near power lines Cleared 12/13/2020 RIDWAN HARDY
Permit Cleared 2/10/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/19/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Approved CHARLES POWELL
PLUMBING-Rough 4/19/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 4/27/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 4/27/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/27/2021 Approved ARTHUR SARGSYAN
Insulation 5/7/2021 Corrections Issued MORRIS JACKSON
Pre-Inspection 5/7/2021 Partial Inspection ALIZAH MAYAGOITIA
Drywall Nailing 5/17/2021 Approved ARTHUR SARGSYAN
Green Building Rough 5/17/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/10/2021 Approved JACK KARGODORIAN
Final 9/10/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 9/10/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/10/2021 Approved JACK KARGODORIAN
Final 9/15/2021 OK to Issue CofO MICHAEL TEMPLE