8511 S BELFORD AVE 90045

Certificate Information: 8511 S BELFORD AVE 90045

Application / Permit
20014-20000-03158
Plan Check / Job No.
B20VN09784
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND (E) BEDROOM, ADD (N) BATHROOM & LAUNDRY ROOM (38'-10" X 8'-6") TO (E) 1-STORY SFD W/ ATTACHED GARAGE
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
CofO Issued on 4/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 NILOOFAR MEHRAIN
Corrections Issued 8/11/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 8/13/2020 APPLICANT
Plan Check Approved 8/28/2020 NILOOFAR MEHRAIN
Issued 8/28/2020 APPLICANT
CofO in Progress 3/11/2021 JOHNNY MIRANDA
Permit Finaled 4/7/2022 DANIEL ORRANTE
CofO Issued 4/7/2022 DANIEL ORRANTE
Permit Finaled 4/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/19/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 8/19/2020 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 8/21/2020 TRACY TATE

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/14/2020 Approved JUAN VALENZUELA
Pre-Inspection 9/14/2020 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 9/21/2020 Partial Inspection JUAN VALENZUELA
Special/Order Compliance 9/21/2020 Partial Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 10/14/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/14/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 10/14/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/2/2020 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/2/2020 Approved JUAN VALENZUELA
HVAC-Rough 11/2/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 11/2/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 11/10/2020 Approved JUAN VALENZUELA
Green Building Rough 11/10/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/10/2020 Partial Approval JUAN VALENZUELA
Insulation 11/16/2020 Approved JUAN VALENZUELA
Drywall Nailing 11/18/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/4/2020 Approved DAVID HEINE
Shower Pan 12/4/2020 Approved DAVID HEINE
ELECTRICAL-Final 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
Final 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 2/26/2021 Approved DAVID HEINE
Final 2/26/2021 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 2/26/2021 Approved DAVID HEINE
Green Building Final 2/26/2021 Approved DAVID HEINE
HVAC-Final 2/26/2021 Approved DAVID HEINE
PLUMBING-Final 2/26/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Gas Company DAVID HEINE
Smoke Detectors 2/26/2021 Approved DAVID HEINE
Final 3/10/2021 OK to Issue CofO JOHNNY MIRANDA
Service/Power Release 3/16/2021 Approved JUAN VALENZUELA