8511 S BELFORD AVE 90045
Certificate Information: 8511 S BELFORD AVE 90045
- Application / Permit
- 20014-20000-03158
- Plan Check / Job No.
- B20VN09784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND (E) BEDROOM, ADD (N) BATHROOM & LAUNDRY ROOM (38'-10" X 8'-6") TO (E) 1-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 8/28/2020
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/11/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 8/13/2020 | APPLICANT |
| Plan Check Approved | 8/28/2020 | NILOOFAR MEHRAIN |
| Issued | 8/28/2020 | APPLICANT |
| CofO in Progress | 3/11/2021 | JOHNNY MIRANDA |
| Permit Finaled | 4/7/2022 | DANIEL ORRANTE |
| CofO Issued | 4/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/19/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 8/19/2020 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Approved | JUAN VALENZUELA |
| Pre-Inspection | 9/14/2020 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/21/2020 | Partial Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 9/21/2020 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/14/2020 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 10/14/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 10/14/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/2/2020 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/2/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 11/2/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 11/2/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/10/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 11/10/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/10/2020 | Partial Approval | JUAN VALENZUELA |
| Insulation | 11/16/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 11/18/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/4/2020 | Approved | DAVID HEINE |
| Shower Pan | 12/4/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 2/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/26/2021 | Approved | DAVID HEINE |
| Final | 2/26/2021 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 2/26/2021 | Approved | DAVID HEINE |
| Green Building Final | 2/26/2021 | Approved | DAVID HEINE |
| HVAC-Final | 2/26/2021 | Approved | DAVID HEINE |
| PLUMBING-Final | 2/26/2021 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Gas Company | DAVID HEINE |
| Smoke Detectors | 2/26/2021 | Approved | DAVID HEINE |
| Final | 3/10/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Service/Power Release | 3/16/2021 | Approved | JUAN VALENZUELA |