6402 W DAY ST 91042
Certificate Information: 6402 W DAY ST 91042
- Application / Permit
- 20014-20000-03155
- Plan Check / Job No.
- B20VN09759
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18' X 10' ADDITION FOR NEW BATHROOM AT REAR OF (E) SFD AND CONNECT TO (E) DETACHED GARAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- CofO Issued on 10/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | ROSENDO MEDINA |
| Corrections Issued | 7/29/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 9/18/2020 | ROSENDO MEDINA |
| Plan Check Approved | 10/28/2020 | ROSENDO MEDINA |
| Issued | 10/28/2020 | APPLICANT |
| CofO in Progress | 5/6/2021 | MATTHEW NELSON |
| Permit Finaled | 10/9/2021 | MICHAEL SMITH |
| CofO Issued | 10/9/2021 | MICHAEL SMITH |
| Permit Finaled | 10/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/21/2020 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/5/2021 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/9/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 2/17/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/8/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/8/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/8/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/8/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 3/11/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/15/2021 | Approved | MATTHEW NELSON |
| Insulation | 3/22/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/24/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/30/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/6/2021 | Approved | MATTHEW NELSON |
| Final | 5/6/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 5/6/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 5/6/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/6/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/6/2021 | Approved | MATTHEW NELSON |