13369 W OSCAR ST 91342

Certificate Information: 13369 W OSCAR ST 91342

Application / Permit
20014-20000-03127
Plan Check / Job No.
B20VN09680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-1" X 28'-4" IRREG SHAPED ADDITION FOR NEW LIVING ROOM. INTERIOR REMODEL TO RELOCATE LAUNDRY ROOM AND CONVERT (E) BEDROOM TO FAMILY ROOM. ALL WORK PER ENGINEER.
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 7/31/2020 JEROME MAGAT PALMA
Corrections Issued 8/3/2020 JEROME MAGAT PALMA
Plan Check Approved 9/24/2020 JEROME MAGAT PALMA
Issued 10/27/2020 APPLICANT
CofO in Progress 8/16/2022 ARAM AVEDISIAN
CofO in Progress 8/26/2022 ROBERT GOLD
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/6/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/10/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Velasco,, Jose Luis; Lic. No.: C76091 100 SE 2ND STREET SUITE 2000      MIAMI, FL 33131

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/24/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/14/2021 Partial Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/23/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/23/2021 Approved MICHEL ABAJAN
Green Building Rough 11/23/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved JOHN HAYES
Insulation 12/3/2021 Approved JOHN HAYES
Interior/Exterior Lathing 12/3/2021 Partial Approval JOHN HAYES
Drywall Nailing 12/13/2021 Approved JOHN HAYES
Final 4/4/2022 Corrections Issued JOHN HAYES
Green Building Final 4/4/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/4/2022 Not Ready for Inspection JOHN HAYES
Final 7/27/2022 OK to Issue CofO DEANDRE HOFFMAN
Green Building Final 7/27/2022 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 7/27/2022 Approved DEANDRE HOFFMAN