12312 W ROSCOE BLVD 91352

Certificate Information: 12312 W ROSCOE BLVD 91352

Application / Permit
20014-20000-03124
Plan Check / Job No.
B20VN09676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'-0" X 21'-0" ADDITION FOR NEW MASTER BEDROOM, WALK-IN CLOSET, AND BATHROOM PER WFPP
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
CofO Issued on 11/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 JEROME MAGAT PALMA
Corrections Issued 8/4/2020 JEROME MAGAT PALMA
Plan Check Approved 9/30/2020 JEROME MAGAT PALMA
Issued 10/8/2020 APPLICANT
Refund in Progress-Status Void 5/12/2021 TERENCE SHIA
Re-Activate Permit 10/6/2021 CANDICE JUSAY
CofO in Progress 10/28/2021 CHRISTOPHER DELLEFIELD
CofO Issued 11/20/2021 MICHAEL SMITH
Permit Finaled 11/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2020 GUILLERMO PETRA
Sewer availability Cleared 8/12/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/14/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2020 Partial Approval JOHN HAYES
Underground Mechanical 11/13/2020 Approved JOHN HAYES
Deputy Drilled-In Anchors 11/18/2020 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 11/30/2020 Approved JOHN HAYES
Footing/Foundation/Slab 11/30/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 12/9/2020 Partial Approval JOHN HAYES
Green Building Rough 12/9/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/20/2021 Partial Approval JOHN HAYES
Green Building Rough 1/20/2021 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 1/20/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/25/2021 Approved JOHN HAYES
Green Building Rough 1/25/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 1/25/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Not Ready for Inspection JOHN HAYES
Insulation 2/10/2021 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 3/1/2021 Partial Approval JOHN HAYES
Drywall Nailing 3/5/2021 Approved JOHN HAYES
Interior/Exterior Lathing 3/11/2021 Approved JOHN HAYES
Interior/Exterior Lathing 3/30/2021 Approved JOHN HAYES
Final 10/14/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/14/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 10/14/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/28/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/28/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 10/28/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/28/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 10/28/2021 Approved CHRISTOPHER DELLEFIELD