7107 N VANSCOY AVE 91605

Certificate Information: 7107 N VANSCOY AVE 91605

Application / Permit
20014-20000-03105
Plan Check / Job No.
B20VN09641
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 8'-5" x 12'-0" ONE STORY ADDITION TO THE REAR OF (E) SINGLE FAMILY DWELLING TO EXPAND FAMILY ROOM AND REMODEL THE FRONT FACADE.
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 8/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 CRISTINA SALAZAR
Corrections Issued 8/17/2020 CRISTINA SALAZAR
Applicant returned to address corrections 9/16/2020 SARKIS HARABEDIAN
Plan Check Approved 2/4/2021 SARKIS HARABEDIAN
Issued 2/4/2021 APPLICANT
CofO in Progress 8/20/2021 CHRISTOPHE COCHRAN
CofO Issued 8/15/2022 DANIEL ORRANTE
Permit Finaled 8/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 9/9/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/15/2021 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 3/16/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/23/2021 Partial Approval THOMAS FINNILA
Green Building Rough 3/23/2021 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Partial Approval ARAM AVEDISIAN
Insulation 7/6/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/6/2021 Approved MORRIS JACKSON
Insulation 7/8/2021 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 7/8/2021 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 7/16/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/3/2021 Approved CHRISTOPHE COCHRAN
Final 8/3/2021 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/3/2021 Approved CHRISTOPHE COCHRAN
Green Building Final 8/3/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/3/2021 Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/3/2021 Approved CHRISTOPHE COCHRAN
Final 8/20/2021 OK to Issue CofO CHRISTOPHE COCHRAN