1830 W CHICKASAW AVE 90041

Certificate Information: 1830 W CHICKASAW AVE 90041

Application / Permit
20014-20000-03091
Plan Check / Job No.
B20VN09620
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
32'-11" X 21'-4" 2ND FLOOR ADDITION & REMODEL TO (E) SFD
Permit Issued
Issued on 1/18/2023
Issuing Office
Current Status
Issued on 1/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 MARVEL DELACRUZ
Corrections Issued 8/20/2020 MARVEL DELACRUZ
Quality Review Completed 8/25/2020 STEVEN KIM
Building Plans Picked Up 8/26/2020 APPLICANT
Applicant returned to address corrections 3/11/2021 MARVEL DELACRUZ
Applicant returned to address corrections 5/10/2021 MARVEL DELACRUZ
Applicant returned to address corrections 4/11/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/31/2022 RAPHAEL ROSAS
Plan Check Approved 8/30/2022 RAPHAEL ROSAS
Issued 1/18/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/3/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 9/3/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 9/3/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 9/3/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 9/3/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 9/4/2020 ELAINE LEI
Distance to fire station Cleared 10/2/2020 MATTHEW CRAIG
Low Impact Development Cleared 1/13/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 2/1/2021 THOMAS LANG
Sewer availability Cleared 2/4/2021 THOMAS LANG
Green Code Cleared 3/11/2021 MARVEL DELACRUZ
GPI Written Notices Cleared 5/10/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/10/2024 Not Ready for Inspection ROY SPAULDING
Deputy Drilled-In Anchors 11/8/2024 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 11/18/2024 Partial Approval ROY SPAULDING
Deputy Drilled-In Anchors 12/4/2024 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 12/5/2024 Approved ROY SPAULDING
Deputy Drilled-In Anchors 1/8/2025 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 1/10/2025 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 2/13/2025 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 2/18/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 2/21/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 5/15/2025 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 7/18/2025 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 8/5/2025 Conditional Approval DAVID WILLIAMS
Footing/Foundation/Slab 8/8/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Partial Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Approved RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Partial Approval RONNIE MEDINA
Deputy Wood Construction 5/26/2026 Conditional Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Approved RONNIE MEDINA
Wood Frame 5/26/2026 Not Ready for Inspection RONNIE MEDINA