10347 1/2 N JORDAN AVE 91311
Certificate Information: 10347 1/2 N JORDAN AVE 91311
- Application / Permit
- 20014-20000-03089
- Plan Check / Job No.
- B20VN09618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 16'-7" X 12'-0" ADDITION TO AND CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER WFPP.
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | ROSENDO MEDINA |
| Corrections Issued | 8/1/2020 | ROSENDO MEDINA |
| Plan Check Approved | 2/25/2021 | ROSENDO MEDINA |
| Issued | 2/26/2021 | APPLICANT |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| CofO in Progress | 2/8/2022 | TROY SANDERS |
| CofO Issued | 2/16/2022 | JOHN JANSON |
| Permit Finaled | 2/16/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/28/2020 | BARTON HOLMES |
Contact Information
| Contractor | Ochoa Victor Manuel; Lic. No.: 908306-B | 13700 FOOTHILL BLVD #920151 SYLMAR, CA 91342 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 5/17/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/24/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 5/24/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/25/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/25/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 6/25/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 6/25/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 8/2/2021 | Approved | DAVID STEPANYAN |
| Insulation | 9/16/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/21/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/21/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/21/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/21/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/21/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 11/15/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/15/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 11/19/2021 | Approved | DAVID STEPANYAN |
| Sewer | 11/19/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/20/2021 | Approved | TROY SANDERS |
| HVAC-Final | 12/20/2021 | Approved | TROY SANDERS |
| PLUMBING-Final | 12/20/2021 | Not Ready for Inspection | TROY SANDERS |
| Gas Test | 1/24/2022 | Approved | JESUS PINEDA |
| Final | 2/8/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/8/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 2/8/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/8/2022 | Approved | TROY SANDERS |