7341 N OAK PARK AVE 91406

Certificate Information: 7341 N OAK PARK AVE 91406

Application / Permit
20014-20000-03071
Plan Check / Job No.
B20VN09576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 24'-4" x 14'-1.5" IRREGULAR SHAPED ADDITION AT REAR FOR NEW MASTER BEDROOM/BATHROOM , 18'-0" x 6'-7" ADDITION FOR UNCOVERED DECK AT REAR, 7'-8" x 6'-0.5" ADDITION AT FRONT FOR ENTRY AND 23'-0.5" x 13'-2.5" IRRULAR SHAPED ADDITION AT FRONT FOR (N)KITCHEN AND INTERIOR REMODEL TO (E)SINGLE FAMILY DWELLING.
Permit Issued
Issued on 10/7/2020
Issuing Office
Current Status
CofO Issued on 6/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 SARKIS HARABEDIAN
Corrections Issued 7/30/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 9/28/2020 SARKIS HARABEDIAN
Plan Check Approved 9/28/2020 SARKIS HARABEDIAN
No Progress 9/28/2020 SARKIS HARABEDIAN
Plan Check Approved 10/7/2020 SARKIS HARABEDIAN
Issued 10/7/2020 APPLICANT
CofO in Progress 3/4/2021 ARTHUR SARGSYAN
CofO in Progress 3/4/2021 ARTHUR SARGSYAN
Permit Finaled 6/12/2021 MICHAEL SMITH
CofO Issued 6/12/2021 MICHAEL SMITH
Permit Finaled 6/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/14/2020 GUILLERMO PETRA
Sewer availability Cleared 9/16/2020 GUILLERMO PETRA
Low Impact Development Cleared 9/22/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/30/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/14/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/14/2020 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/20/2020 Approved MICHAEL TEMPLE
Footing/Foundation/Slab 10/20/2020 Approved MICHAEL TEMPLE
Insulation 11/5/2020 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 11/5/2020 Partial Approval ARTHUR SARGSYAN
Sewer 11/5/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 11/19/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 11/23/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 11/30/2020 Approved ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 11/30/2020 Approved ARTHUR SARGSYAN
Insulation 12/1/2020 Approved ARTHUR SARGSYAN
Wood Frame 12/1/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 12/11/2020 Approved ARTHUR SARGSYAN
Green Building Rough 12/11/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/16/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 2/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 2/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/3/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 2/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/4/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/4/2021 Approved ARTHUR SARGSYAN
Final 3/4/2021 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 3/4/2021 Approved ARTHUR SARGSYAN
HVAC-Final 3/4/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 3/4/2021 Approved ARTHUR SARGSYAN
Smoke Detectors 3/4/2021 Approved ARTHUR SARGSYAN