10556 W ROSCOE BLVD 91352
Certificate Information: 10556 W ROSCOE BLVD 91352
- Application / Permit
- 20014-20000-03070
- Plan Check / Job No.
- B20VN09571
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14'-7" X 20' ADDITION TO (E) RECREATION ROOM AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 12/15/2020
- Issuing Office
- Current Status
- CofO Issued on 6/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | SERGIO MUNIZ |
| Corrections Issued | 8/5/2020 | SERGIO MUNIZ |
| Building Plans Picked Up | 8/5/2020 | APPLICANT |
| Applicant returned to address corrections | 12/6/2020 | SERGIO MUNIZ |
| Plan Check Approved | 12/13/2020 | SERGIO MUNIZ |
| Issued | 12/15/2020 | APPLICANT |
| CofO in Progress | 12/23/2021 | WILLIAM KUEHN |
| CofO Issued | 6/30/2022 | MICHAEL SMITH |
| Permit Finaled | 6/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/18/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/28/2020 | GUILLERMO PETRA |
| Hold | Cleared | 2/11/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2021 | Partial Inspection | BEAU COLLINS |
| Footing/Foundation/Slab | 5/14/2021 | Approved | MATTHEW NELSON |
| Pre-Inspection | 6/2/2021 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/23/2021 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 8/23/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/27/2021 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/27/2021 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/27/2021 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/27/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/1/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/1/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 10/1/2021 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 10/1/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/7/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/13/2021 | Approved | WILLIAM KUEHN |
| Final | 12/13/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 12/13/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Rough | 12/13/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| MERV13>=Final | 12/13/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Not Ready | WILLIAM KUEHN |
| Smoke Detectors | 12/13/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | WILLIAM KUEHN |
| Final | 12/22/2021 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 12/22/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 12/22/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 12/22/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | WILLIAM KUEHN |