9515 N BURNET AVE 91343
Certificate Information: 9515 N BURNET AVE 91343
- Application / Permit
- 20014-20000-03069
- Plan Check / Job No.
- B20VN09569
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, AND (N) 16'-8" X 54'-1.5" ONE STORY IRREGULAR SHAPED ADDITION TO SINGLE FAMILY DWELLING TO ENLARGE LIVING ROOM, ADD STUDY ROOM, MASTER BEDROOM ALL WORK PER ENGINEERING NFPA 13D FIRE SPRINKLERS REQUIRED
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/10/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| Applicant returned to address corrections | 7/7/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 7/14/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/5/2021 | APPLICANT |
| CofO in Progress | 6/6/2024 | ROBERT GOLD |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 5/17/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | GABRIEL ROBLES |
Contact Information
| Architect | , ; Lic. No.: C35995 | , |
| Contractor | Owner-Builder | , |
| Engineer | Lambert,, Will A; Lic. No.: S5430 | 223 E THOUSAND OAKS BLVD304 THOUSAND OAKS, CA 91360 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/12/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 4/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/20/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| Insulation | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/12/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 5/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 7/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 8/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/25/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/25/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/25/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/28/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/8/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 11/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/19/2022 | Conditional Approval | MICHAEL SMITH |
| Deputy Wood Construction | 1/12/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Drilled-In Anchors | 6/22/2023 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 6/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 6/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/3/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/3/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 7/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 7/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/19/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/20/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/4/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/4/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 12/4/2023 | Approved | MICHEL ABAJAN |
| Final | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 6/6/2024 | OK to Issue CofO | ROBERT GOLD |