5530 N AURA AVE 91356

Certificate Information: 5530 N AURA AVE 91356

Application / Permit
20014-20000-03063
Plan Check / Job No.
B20VN09551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT (E) GARAGE TO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 2/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/7/2020 RAHEL BEYENE
Corrections Issued 8/10/2020 RAHEL BEYENE
Applicant returned to address corrections 3/1/2022 RAHEL BEYENE
Plan Check Approved 4/1/2022 MINA HABILI
Building Plans Picked Up 4/22/2022 APPLICANT
Issued 2/1/2023 APPLICANT
CofO in Progress 3/11/2025 JOHN KIDWELL
Permit Finaled 4/2/2025 JOHN JANSON
CofO Issued 4/2/2025 JOHN JANSON
Permit Finaled 4/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/12/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/14/2021 GUILLERMO PETRA
Sewer availability Cleared 1/14/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 1/27/2021 BARTON HOLMES
Hydrant and Access approval Cleared 2/26/2021 MATTHEW CRAIG
Construction near power lines Cleared 8/10/2021 RIDWAN HARDY
Low Impact Development Cleared 3/22/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/23/2022 JOHN LIN

Contact Information

Contractor Quality Tech Construction Inc; Lic. No.: 1026398-B 967 ROYAL AVENUE      SIMI VALLEY, CA 93065
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2023 Approved JON MCHUGH
PLUMBING-Rough 4/13/2023 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 4/18/2023 Approved JUSTIN HAWLEY
Pre-Inspection 4/18/2023 Approved DAVID SANDOVAL
Deputy Drilled-In Anchors 4/20/2023 Partial Approval DAVID SANDOVAL
Deputy Reinf. Concrete 4/24/2023 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 4/25/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 4/25/2023 Approved SEAN HAUPT
Special/Order Compliance 4/25/2023 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval MORRIS JACKSON
Rough-Elec/Plmb/HVAC 7/19/2023 Approved SEAN HAUPT
Gas Test 7/25/2023 Not Ready for Inspection SEAN HAUPT
Insulation 7/25/2023 Approved SEAN HAUPT
Gas Test 7/27/2023 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 8/2/2023 Partial Approval MORRIS JACKSON
Drywall Nailing 8/2/2023 Approved MORRIS JACKSON
Shower Pan 9/15/2023 Approved SEAN HAUPT
Sewer 11/30/2023 Approved SEAN HAUPT
Gas Test 5/3/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/12/2024 Approved JOHN KIDWELL
Final 9/12/2024 Corrections Issued JOHN KIDWELL
Green Building Final 9/12/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 9/12/2024 Approved JOHN KIDWELL
MERV13>=Final 9/12/2024 Approved JOHN KIDWELL
MERV13>=Rough 9/12/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 9/12/2024 Approved JOHN KIDWELL
Green Building Final 1/14/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Approved JOHN KIDWELL
Service/Power Release 1/14/2025 Approved JOHN KIDWELL
Final 1/27/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 1/27/2025 Not Ready for Inspection JOHN KIDWELL
Final 3/4/2025 OK to Issue CofO JOHN KIDWELL
Green Building Final 3/4/2025 Approved JOHN KIDWELL