17201 W HART ST 91406
Certificate Information: 17201 W HART ST 91406
- Application / Permit
- 20014-20000-03058
- Plan Check / Job No.
- B20VN09537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'-8" X 13'-3" ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/18/2020 | SELLA BENYAMIN |
| Quality Review Completed | 8/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/26/2020 | APPLICANT |
| Plan Check Approved | 9/21/2020 | SELLA BENYAMIN |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 9/23/2022 | SEAN HAUPT |
| Permit Finaled | 10/6/2022 | JOHN JANSON |
| CofO Issued | 10/6/2022 | JOHN JANSON |
| Permit Finaled | 10/6/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 9/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/14/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 12/7/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/11/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2020 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 3/5/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 3/5/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/5/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 3/12/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/12/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 3/24/2021 | Partial Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 8/24/2021 | Partial Approval | RYAN SALAZAR |
| Insulation | 9/21/2021 | Partial Approval | KRISTEN CAUSEY |
| Drywall Nailing | 12/8/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/13/2021 | Approved | SEAN HAUPT |
| Shower Pan | 1/26/2022 | Approved | RYAN SALAZAR |
| Insulation | 2/15/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/15/2022 | Approved | JUSTIN HAWLEY |
| Gas Test | 5/12/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | SEAN HAUPT |
| Final | 9/9/2022 | Corrections Issued | SEAN HAUPT |
| Gas Test | 9/9/2022 | Approved | SEAN HAUPT |
| Green Building Final | 9/9/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 9/9/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 9/9/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 9/22/2022 | Partial Approval | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 9/22/2022 | Approved | SEAN HAUPT |