13574 W JUDD ST 91331
Certificate Information: 13574 W JUDD ST 91331
- Application / Permit
- 20014-20000-03051
- Plan Check / Job No.
- B20VN09523
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 10'-9" x 20'-0" ADDITION TOO AND CONVERT THE (E) ACCESSORY LIVING QUARTERS INTO A (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP. COMPLY WITH DEPARTMENT ORDER effective date 07/30/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 7/30/2020 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 6/2/2023 | JESSE ARELLANO |
| Plan Check Approved | 7/21/2023 | ALFRED RAMIREZ |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 1/31/2024 | AGUSTIN ALVAREZMORALES |
| Permit Finaled | 4/25/2024 | DAVID JAMES |
| CofO Issued | 4/25/2024 | DAVID JAMES |
| Permit Finaled | 4/25/2024 | DAVID JAMES |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
| Address approval | Cleared | 12/2/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/10/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Deputy Other (see comments) | 10/31/2023 | No Access for Inspection | AGUSTIN ALVAREZMORALES |
| BUILDING-Rough-Frame | 11/6/2023 | Partial Inspection | AGUSTIN ALVAREZMORALES |
| Deputy Wood Construction | 11/6/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Green Building Rough | 11/6/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| METHANE-Rough | 11/6/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Footing/Foundation/Slab | 11/14/2023 | No Access for Inspection | AGUSTIN ALVAREZMORALES |
| METHANE-Barrier | 11/14/2023 | No Access for Inspection | AGUSTIN ALVAREZMORALES |
| METHANE-Subgrade | 11/14/2023 | No Access for Inspection | AGUSTIN ALVAREZMORALES |
| Rough-Elec/Plmb/HVAC | 11/14/2023 | No Access for Inspection | AGUSTIN ALVAREZMORALES |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Rough | 12/4/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| PLUMBING-Rough | 12/4/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Drywall Nailing | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Footing/Foundation/Slab | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Green Building Rough | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Insulation | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Interior/Exterior Lathing | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| METHANE-Barrier | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| METHANE-Subgrade | 12/15/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 1/11/2024 | Conditional Approval | AGUSTIN ALVAREZMORALES |
| Green Building Final | 1/11/2024 | Approved | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Approved | AGUSTIN ALVAREZMORALES |
| Smoke Detectors | 1/11/2024 | Approved | AGUSTIN ALVAREZMORALES |