11322 W ELDERWOOD ST 90049
Certificate Information: 11322 W ELDERWOOD ST 90049
- Application / Permit
- 20014-20000-03038
- Plan Check / Job No.
- B20VN09490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13' 7" X 16' IRR.-SHAPE ENTRY & LAUNDRY ADDITION, 25' 4" X 16' MASTER/BEDROOM/BATHROOM/CLOSET ADDITION TO REAR, REMODEL KITCHEN AND REMODEL 41' 10" X 13' PORTION OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 7/28/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/5/2021 | GURUNATH NESARAJAH |
| Issued | 4/9/2021 | APPLICANT |
| Building Plans Picked Up | 4/13/2021 | APPLICANT |
| CofO in Progress | 3/8/2023 | CARLOS MATAMOROS |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
| CofO Issued | 3/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/1/2020 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 1/7/2021 | MITESH PATEL |
| GPI Written Notices | Cleared | 1/27/2021 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 1/27/2021 | GURUNATH NESARAJAH |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | CATHERINE ADROVER |
Contact Information
| Contractor | Luxe Development Inc; Lic. No.: 993473-B | 329 N WETHERLY DRIVE #205 BEVERLY HILLS, CA 90211 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/3/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/5/2021 | Approved | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 5/18/2021 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 5/18/2021 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 5/24/2021 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 8/17/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 8/17/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 8/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/23/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 8/23/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/23/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 8/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| MERV13>=Rough | 8/23/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/23/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/1/2021 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/1/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 9/1/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 9/1/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/1/2021 | Approved | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 9/1/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/10/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/10/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 9/10/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 9/27/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/27/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/27/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/29/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 10/1/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/19/2021 | Approved | CARLOS MATAMOROS |
| Final | 11/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 11/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 11/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 11/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/15/2023 | Corrections Issued | CARLOS MATAMOROS |
| Final | 2/15/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 2/15/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/15/2023 | Corrections Issued | CARLOS MATAMOROS |
| MERV13>=Final | 2/15/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 2/15/2023 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/15/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/7/2023 | Approved | CARLOS MATAMOROS |
| Final | 3/7/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 3/7/2023 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 3/7/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/7/2023 | Approved | CARLOS MATAMOROS |