5634 N BURNET AVE 91411

Certificate Information: 5634 N BURNET AVE 91411

Application / Permit
20014-20000-03006
Plan Check / Job No.
B20VN09412
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-8" X 16'-4" ADDITION TO (E) DWELLING FOR NEW BEDROOM, BATHROOM, AND FAMILY ROOM. REMODEL (E) BATHROOM.
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
CofO Issued on 12/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 JEROME MAGAT PALMA
Corrections Issued 7/26/2020 JEROME MAGAT PALMA
Plan Check Approved 8/6/2020 JEROME MAGAT PALMA
Issued 12/21/2020 APPLICANT
CofO in Progress 7/13/2021 JENNIFER RABUCHIN
CofO Issued 12/11/2021 MICHAEL SMITH
Permit Finaled 12/11/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/31/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/31/2020 ADRIAN CASTRO
Sewer availability Cleared 7/31/2020 ADRIAN CASTRO

Contact Information

Architect , ; Lic. No.: C33595       ,
Contractor United Firm Construction Inc; Lic. No.: 400062-B 1568 LOMA VISTA ST      PASADENA, CA 91104

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 2/17/2021 Approved JOHN HAYES
PLUMBING-Rough 3/18/2021 Corrections Issued BRENDAN LOONEY
Pre-Inspection 3/18/2021 Partial Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 4/8/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 4/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/8/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/8/2021 Approved JENNIFER RABUCHIN
Insulation 4/19/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/19/2021 Partial Approval JENNIFER RABUCHIN
Shower Pan 4/19/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 4/23/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/18/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/12/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/12/2021 Approved JENNIFER RABUCHIN
Final 7/12/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 7/12/2021 Approved JENNIFER RABUCHIN
Green Building Rough 7/12/2021 Approved JENNIFER RABUCHIN
HVAC-Final 7/12/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/12/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/12/2021 Approved JENNIFER RABUCHIN