6504 N VALJEAN AVE 91406
Certificate Information: 6504 N VALJEAN AVE 91406
- Application / Permit
- 20014-20000-03001
- Plan Check / Job No.
- B20VN09394
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-5" X 20'-0" DETACHED GARAGE AND ADD 10'-1" X 20'-0" FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B) AND LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/7/2020
- Issuing Office
- Current Status
- CofO Corrected on 2/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | JENNIFER LEE |
| Corrections Issued | 7/25/2020 | JENNIFER LEE |
| Plan Check Approved | 11/5/2020 | JENNIFER LEE |
| Issued | 11/7/2020 | APPLICANT |
| CofO in Progress | 12/9/2022 | RAUL OLAGI |
| CofO Issued-Status Void | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled-Status Void | 12/17/2022 | MICHAEL SMITH |
| Re-Activate Permit | 2/28/2023 | MICHAEL SMITH |
| CofO Corrected | 2/28/2023 | MICHAEL SMITH |
| Permit Finaled | 2/28/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/27/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/27/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 5/19/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 6/24/2022 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 8/3/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 8/3/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/29/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/29/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/29/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/14/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 9/14/2022 | Approved | RAUL OLAGI |
| Insulation | 9/14/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/14/2022 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 9/21/2022 | Not Ready for Inspection | ALAN MORELOS |
| Underground Mechanical | 9/21/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 9/26/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 10/17/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 11/28/2022 | Corrections Issued | RAUL OLAGI |
| Final | 11/28/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 11/28/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 11/28/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 11/28/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 11/28/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/9/2022 | Approved | RAUL OLAGI |
| Final | 12/9/2022 | OK to Issue CofO | RAUL OLAGI |
| HVAC-Final | 12/9/2022 | Approved | RAUL OLAGI |