1430 S HAUSER BLVD 90019
Certificate Information: 1430 S HAUSER BLVD 90019
- Application / Permit
- 20014-20000-02985
- Plan Check / Job No.
- B20VN09340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 22' X 19' ON FIRST FLOOR AND 42' X 19' ON SECOND FLOOR TO EXISTING DETACHED GARAGE FOR NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) (GARAGE TO REMAIN)
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/10/2020 | SELLA BENYAMIN |
| Quality Review Completed | 8/10/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/11/2020 | APPLICANT |
| Plan Check Approved | 1/15/2021 | SELLA BENYAMIN |
| Issued | 2/8/2021 | APPLICANT |
| CofO in Progress | 2/22/2022 | GLEN RAND |
| Permit Finaled | 2/25/2022 | BRUCE TODD |
| CofO Issued | 2/25/2022 | BRUCE TODD |
| Permit Finaled | 2/25/2022 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/14/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 12/10/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/28/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Alpha Build & Design Inc; Lic. No.: 398659-A | 611 WILSHIRE BLVD #1416 LOS ANGELES, CA 90017 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2021 | Approved | GLEN RAND |
| Pre-Inspection | 2/16/2021 | Approved | GLEN RAND |
| PLUMBING-Rough | 3/1/2021 | Corrections Issued | GLEN RAND |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Approved | GLEN RAND |
| PLUMBING-Rough | 3/4/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2021 | Partial Approval | GLEN RAND |
| Pre-Inspection | 3/24/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | JESSE CHEN |
| HVAC-Rough | 4/26/2021 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 5/3/2021 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 5/3/2021 | Corrections Issued | GLEN RAND |
| METHANE-Rough | 5/19/2021 | Approved | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 5/20/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 6/2/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 6/4/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 6/4/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Approved | GLEN RAND |
| Green Building Rough | 6/4/2021 | Approved | GLEN RAND |
| HVAC-Rough | 6/4/2021 | Approved | GLEN RAND |
| PLUMBING-Rough | 6/4/2021 | Partial Approval | GLEN RAND |
| Shower Pan | 6/4/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 6/15/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 6/15/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 6/29/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 6/29/2021 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 6/29/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 6/29/2021 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 6/29/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 7/6/2021 | Partial Approval | JESSE CHEN |
| ELECTRICAL-Rough | 7/6/2021 | Partial Approval | JESSE CHEN |
| Insulation | 7/15/2021 | Approved | GLEN RAND |
| Drywall Nailing | 7/20/2021 | Corrections Issued | GLEN RAND |
| Interior/Exterior Lathing | 7/20/2021 | Approved | GLEN RAND |
| Drywall Nailing | 7/21/2021 | Approved | GLEN RAND |
| Pre-Inspection | 8/6/2021 | Approved | GLEN RAND |
| Pre-Inspection | 8/31/2021 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 9/17/2021 | Corrections Issued | GLEN RAND |
| METHANE-Barrier | 9/17/2021 | Approved | GLEN RAND |
| METHANE-Subgrade | 9/17/2021 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Not Ready | GLEN RAND |
| Smoke Detectors | 9/17/2021 | Not Ready for Inspection | GLEN RAND |
| Gas Test | 9/21/2021 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 9/21/2021 | Corrections Issued | GLEN RAND |
| Gas Test | 9/27/2021 | Corrections Issued | GLEN RAND |
| Pre-Inspection | 9/27/2021 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 9/30/2021 | Approved | GLEN RAND |
| Gas Test | 9/30/2021 | Approved | GLEN RAND |
| HVAC-Rough | 10/7/2021 | Corrections Issued | GLEN RAND |
| Smoke Detectors | 10/14/2021 | Approved | GLEN RAND |
| ELECTRICAL-Final | 10/25/2021 | Corrections Issued | GLEN RAND |
| Sewer | 10/25/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | GLEN RAND |
| Final | 10/28/2021 | Corrections Issued | GLEN RAND |
| Green Building Final | 10/28/2021 | Corrections Issued | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 10/28/2021 | SGSOV Not Ready | GLEN RAND |
| Gas Test | 11/3/2021 | Approved | GLEN RAND |
| Final | 1/6/2022 | Not Ready for Inspection | GLEN RAND |
| Green Building Final | 1/6/2022 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 1/6/2022 | SGSOV Not Ready | GLEN RAND |
| Final | 1/10/2022 | Not Ready for Inspection | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Not Ready | GLEN RAND |
| Special/Order Compliance | 1/10/2022 | Corrections Issued | GLEN RAND |
| Final | 1/14/2022 | OK to Issue CofO | GLEN RAND |
| Gas Test | 1/14/2022 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 1/14/2022 | Approved | GLEN RAND |
| PLUMBING-Final | 1/14/2022 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Approved | GLEN RAND |