13744 W MERCER ST 91331
Certificate Information: 13744 W MERCER ST 91331
- Application / Permit
- 20014-20000-02982
- Plan Check / Job No.
- B20VN09335
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20' X 20' (E) DETACHED GARAGE AND ADD 26'-10.75" X 34'-3.75" IRREGULAR SHAPED TO CREATE (N) ACCESSORY DWELLING UNIT AND ADD 3'-2" X 6' COVERED PORCH. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | RAPHAEL ROSAS |
| Corrections Issued | 8/11/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 8/11/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 8/11/2020 | APPLICANT |
| Applicant returned to address corrections | 9/29/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 12/9/2020 | RAPHAEL ROSAS |
| Issued | 1/6/2021 | APPLICANT |
| CofO in Progress | 7/19/2021 | MICHEL ABAJAN |
| CofO Issued | 8/21/2021 | MICHAEL SMITH |
| Permit Finaled | 8/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/26/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/1/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/1/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/14/2021 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/15/2021 | Conditional Approval | MICHEL ABAJAN |
| METHANE-Barrier | 1/15/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/15/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/25/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 1/25/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 1/25/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/25/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/26/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/26/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/26/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/26/2021 | Approved | MICHEL ABAJAN |
| Insulation | 3/30/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/6/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/12/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/12/2021 | Approved | MICHEL ABAJAN |
| Final | 6/7/2021 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/7/2021 | Approved | MICHEL ABAJAN |
| Green Building Final | 6/7/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/7/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/19/2021 | Approved | MICHEL ABAJAN |
| Final | 7/19/2021 | OK to Issue CofO | MICHEL ABAJAN |
| PLUMBING-Final | 7/19/2021 | Approved | MICHEL ABAJAN |