13744 W MERCER ST 91331

Certificate Information: 13744 W MERCER ST 91331

Application / Permit
20014-20000-02982
Plan Check / Job No.
B20VN09335
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 20' (E) DETACHED GARAGE AND ADD 26'-10.75" X 34'-3.75" IRREGULAR SHAPED TO CREATE (N) ACCESSORY DWELLING UNIT AND ADD 3'-2" X 6' COVERED PORCH. ALL WORK PER WFPP.
Permit Issued
Issued on 1/6/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/7/2020 RAPHAEL ROSAS
Corrections Issued 8/11/2020 RAPHAEL ROSAS
Quality Review Completed 8/11/2020 CHON CHIO KUO
Building Plans Picked Up 8/11/2020 APPLICANT
Applicant returned to address corrections 9/29/2020 RAPHAEL ROSAS
Plan Check Approved 12/9/2020 RAPHAEL ROSAS
Issued 1/6/2021 APPLICANT
CofO in Progress 7/19/2021 MICHEL ABAJAN
CofO Issued 8/21/2021 MICHAEL SMITH
Permit Finaled 8/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/18/2020 ADRIAN CASTRO
Sewer availability Cleared 9/18/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/26/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/5/2020 ADRIAN CASTRO
Construction near power lines Cleared 12/1/2020 RIDWAN HARDY
Construction within easement Cleared 12/1/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2021 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 1/15/2021 Conditional Approval MICHEL ABAJAN
METHANE-Barrier 1/15/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 1/15/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/25/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 1/25/2021 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 1/25/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 1/25/2021 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 3/26/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/26/2021 Approved MICHEL ABAJAN
Green Building Rough 3/26/2021 Approved MICHEL ABAJAN
HVAC-Final 3/26/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 3/26/2021 Approved MICHEL ABAJAN
Insulation 3/30/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/6/2021 Approved MICHEL ABAJAN
Drywall Nailing 4/12/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/12/2021 Approved MICHEL ABAJAN
Final 6/7/2021 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 6/7/2021 Approved MICHEL ABAJAN
Green Building Final 6/7/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 6/7/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/19/2021 Approved MICHEL ABAJAN
Final 7/19/2021 OK to Issue CofO MICHEL ABAJAN
PLUMBING-Final 7/19/2021 Approved MICHEL ABAJAN