14543 W HESBY ST 91403

Certificate Information: 14543 W HESBY ST 91403

Application / Permit
20014-20000-02967
Plan Check / Job No.
B20VN09321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12'-6" X 27'-2" ADDITION TO (E) SFD FOR (N) BEDROOM, BATHROOM AND WIC. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/5/2020 RAPHAEL ROSAS
Corrections Issued 8/6/2020 RAPHAEL ROSAS
Plan Check Approved 9/21/2020 RAPHAEL ROSAS
Issued 10/6/2020 APPLICANT
CofO in Progress 11/5/2021 JACK KARGODORIAN
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/13/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 8/13/2020 ADRIAN CASTRO
Sewer availability Cleared 8/13/2020 ADRIAN CASTRO
ZI Cleared 8/20/2020 PABLO ESTRADA

Contact Information

Contractor Smart Construction Consultants Inc; Lic. No.: 1040768-B 5805 WHITE OAK AVE STE 17781      ENCINO, CA 91416
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/9/2020 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 10/9/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/14/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 10/21/2020 Corrections Issued CHARLES POWELL
Underground Mechanical 10/21/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 10/26/2020 Partial Approval CHARLES POWELL
Underground Mechanical 10/26/2020 Partial Approval CHARLES POWELL
ELECTRICAL-Rough 10/29/2020 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 10/29/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/4/2020 Partial Approval CHARLES POWELL
ELECTRICAL-Rough 11/23/2020 Approved ARAM AVEDISIAN
HVAC-Rough 11/23/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/23/2020 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 11/23/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 12/1/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 12/1/2020 Approved CHARLES POWELL
Wood Frame 12/1/2020 Corrections Issued CHARLES POWELL
Insulation 12/3/2020 Approved CHARLES POWELL
Insulation 12/8/2020 Approved CHARLES POWELL
Wood Frame 12/8/2020 Approved CHARLES POWELL
Drywall Nailing 12/14/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 12/30/2020 Approved ARTHUR SARGSYAN
Shower Pan 12/30/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/5/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/5/2021 Corrections Issued MISAEL ESPARZA
Final 10/5/2021 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/5/2021 Approved MISAEL ESPARZA
Green Building Final 10/5/2021 Approved MISAEL ESPARZA
Green Building Rough 10/5/2021 Approved MISAEL ESPARZA
HVAC-Final 10/5/2021 Approved MISAEL ESPARZA
PLUMBING-Final 10/5/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 10/5/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 11/5/2021 Approved JACK KARGODORIAN
Final 11/5/2021 OK to Issue CofO JACK KARGODORIAN
HVAC-Final 11/5/2021 Approved JACK KARGODORIAN
PLUMBING-Final 11/5/2021 Approved JACK KARGODORIAN
Smoke Detectors 11/5/2021 Approved JACK KARGODORIAN