11603 W HESBY ST 91601
Certificate Information: 11603 W HESBY ST 91601
- Application / Permit
- 20014-20000-02949
- Plan Check / Job No.
- B20VN09255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 49'-6" X 59'-9" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING AND REMODEL TO RECONFIGURE FLOOR PLAN AND ADD NEW ATTACHED GARAGE; EQUPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/27/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/10/2020 | SELLA BENYAMIN |
| Quality Review Completed | 8/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/14/2020 | APPLICANT |
| Applicant returned to address corrections | 12/17/2020 | SELLA BENYAMIN |
| Plan Check Approved | 12/29/2020 | SELLA BENYAMIN |
| Issued | 1/27/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | MATT KELLERMAN |
| CofO in Progress | 7/13/2022 | MATT KELLERMAN |
| No Progress | 7/16/2022 | MICHAEL SMITH |
| CofO in Progress | 8/30/2022 | MICHAEL SMITH |
| No Progress | 8/30/2022 | MICHAEL SMITH |
| CofO in Progress | 8/30/2022 | MICHAEL SMITH |
| CofO Issued | 8/30/2022 | MICHAEL SMITH |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/18/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/13/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 12/2/2020 | OLGA AYALA |
Contact Information
| Contractor | Berardinelli Custom Builders; Lic. No.: 884217-B | 3483 OLD CONEJO RD STE 204 NEWBURY PARK, CA 91320 |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 22647 VENTURA BLVD 362 WOODLAND HILLS, CA 91364 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/9/2021 | Partial Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/24/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/24/2021 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 2/24/2021 | Off-Hour Fees Due | |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 3/2/2021 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 3/4/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 3/4/2021 | Off-Hour Fees Due | |
| Wood Frame | 3/10/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 4/16/2021 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 4/27/2021 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 5/18/2021 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/24/2021 | Corrections Issued | ALAN MORELOS |
| Deputy Wood Construction | 5/25/2021 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/1/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/2/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 6/2/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/2/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/2/2021 | Approved | THOMAS FINNILA |
| Insulation | 6/9/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 6/16/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/16/2021 | Partial Approval | MORRIS JACKSON |
| Special/Order Compliance | 6/16/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/21/2021 | Partial Approval | ALAN MORELOS |
| Shower Pan | 6/21/2021 | Approved | ALAN MORELOS |
| Underground Mechanical | 7/26/2021 | Partial Approval | WILLIAM KUEHN |
| ELECTRICAL-Final | 10/21/2021 | Partial Inspection | THOMAS FINNILA |
| Gas Test | 10/22/2021 | Approved | THOMAS FINNILA |
| HVAC-Final | 10/22/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 10/22/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 10/26/2021 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/27/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 10/27/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 10/27/2021 | Approved | THOMAS FINNILA |
| Pre-Inspection | 11/2/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 1/6/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | DAVID MATSON |
| Final | 3/17/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 3/17/2022 | Approved | DAVID MATSON |
| Green Building Final | 3/17/2022 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 3/17/2022 | Corrections Issued | DAVID MATSON |
| Final | 4/26/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 4/26/2022 | Corrections Issued | DAVID MATSON |
| Final | 6/7/2022 | Conditional Approval | MATT KELLERMAN |
| Green Building Final | 6/7/2022 | Approved | MATT KELLERMAN |
| Smoke Detectors | 6/7/2022 | Approved | MATT KELLERMAN |
| Final | 7/13/2022 | OK to Issue CofO | MATT KELLERMAN |