10524 N ALDEA AVE 91344
Certificate Information: 10524 N ALDEA AVE 91344
- Application / Permit
- 20014-20000-02925
- Plan Check / Job No.
- B20VN09192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 8'-0" X 17'-6" DETACHED GARAGE AND ADD IRREGULAR 20'-9" X 32'-6" FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B), ATTACH TO (E) 20'-9" X 24'-9" GARAGE.
- Permit Issued
- Issued on 5/14/2021
- Issuing Office
- Current Status
- CofO Corrected on 2/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | JENNIFER LEE |
| Corrections Issued | 7/23/2020 | JENNIFER LEE |
| Plan Check Approved | 12/28/2020 | JENNIFER LEE |
| Issued | 5/14/2021 | APPLICANT |
| CofO in Progress | 1/28/2022 | JEFFREY PARD |
| Re-Activate Permit | 2/9/2022 | JOHN JANSON |
| CofO Issued-Status Void | 2/9/2022 | JOHN JANSON |
| Permit Finaled-Status Void | 2/9/2022 | JOHN JANSON |
| CofO Corrected | 2/9/2022 | JOHN JANSON |
| Permit Finaled | 2/9/2022 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/2/2020 | YVAINNE GALSIM |
| Address approval | Cleared | 12/17/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/17/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/17/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | United Remodeling Construction Inc; Lic. No.: 813590-B | 4924 BALBOA BLVD #447 ENCINO, CA 91316 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2021 | Partial Approval | JEFFREY PARD |
| Sewer | 6/28/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 7/1/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/27/2021 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 8/27/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 8/27/2021 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 8/27/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/8/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 9/8/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 9/8/2021 | Approved | JEFFREY PARD |
| Insulation | 9/13/2021 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/13/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 9/13/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/17/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 9/17/2021 | Approved | JEFFREY PARD |
| Final | 12/1/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 12/1/2021 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 12/1/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 1/6/2022 | Approved | JEFFREY PARD |
| Final | 1/6/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 1/6/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Final | 1/6/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 1/6/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 1/6/2022 | SGSOV Approved | JEFFREY PARD |
| Final | 1/26/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 1/26/2022 | Approved | JEFFREY PARD |