8064 S ALTAVAN AVE 90045

Certificate Information: 8064 S ALTAVAN AVE 90045

Application / Permit
20014-20000-02914
Plan Check / Job No.
B20VN09148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-4" X 14'-11" IRREG SHAPED ADDITION TO ENLARGE (E) BEDROOM AND ADD NEW BATHROOM PER ENGINEER
Permit Issued
Issued on 9/3/2020
Issuing Office
Current Status
CofO Issued on 4/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 JEROME MAGAT PALMA
Corrections Issued 7/18/2020 JEROME MAGAT PALMA
Plan Check Approved 8/14/2020 RARES BODEA
Issued 9/3/2020 APPLICANT
CofO in Progress 12/15/2020 JUAN VALENZUELA
Permit Finaled 4/7/2022 DANIEL ORRANTE
CofO Issued 4/7/2022 DANIEL ORRANTE
Permit Finaled 4/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 7/22/2020 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 7/27/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 7/27/2020 EMIL KYUPELYAN

Contact Information

Contractor Precise Home Builders Inc; Lic. No.: 515469-B 6925 CANBY AVE STE #103      RESEDA, CA 91335
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 5649 VANTAGE AVE      VALLEY VILLAGE, CA 91607

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2020 Conditional Approval JUAN VALENZUELA
METHANE-Barrier 9/8/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 9/8/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 9/14/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 10/2/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 10/2/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 10/2/2020 Approved JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 10/2/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 10/6/2020 Approved JUAN VALENZUELA
HVAC-Rough 10/6/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 10/6/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 10/8/2020 Approved JUAN VALENZUELA
Green Building Rough 10/8/2020 Approved JUAN VALENZUELA
Insulation 10/8/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/8/2020 Partial Approval JUAN VALENZUELA
Shower Pan 10/14/2020 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 10/15/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/15/2020 Approved JUAN VALENZUELA
Shower Pan 10/15/2020 Corrections Issued JUAN VALENZUELA
Shower Pan 10/20/2020 Approved JUAN VALENZUELA
Final 11/18/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 11/18/2020 Approved JUAN VALENZUELA
Green Building Final 11/18/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 11/18/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 12/15/2020 Approved JUAN VALENZUELA
Final 12/15/2020 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 12/15/2020 Approved JUAN VALENZUELA
PLUMBING-Final 12/15/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved JUAN VALENZUELA