8064 S ALTAVAN AVE 90045
Certificate Information: 8064 S ALTAVAN AVE 90045
- Application / Permit
- 20014-20000-02914
- Plan Check / Job No.
- B20VN09148
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-4" X 14'-11" IRREG SHAPED ADDITION TO ENLARGE (E) BEDROOM AND ADD NEW BATHROOM PER ENGINEER
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/18/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/14/2020 | RARES BODEA |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 12/15/2020 | JUAN VALENZUELA |
| Permit Finaled | 4/7/2022 | DANIEL ORRANTE |
| CofO Issued | 4/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 7/22/2020 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 7/27/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Precise Home Builders Inc; Lic. No.: 515469-B | 6925 CANBY AVE STE #103 RESEDA, CA 91335 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 5649 VANTAGE AVE VALLEY VILLAGE, CA 91607 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2020 | Conditional Approval | JUAN VALENZUELA |
| METHANE-Barrier | 9/8/2020 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 9/8/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/14/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/2/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 10/2/2020 | Approved | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 10/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/6/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 10/6/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 10/6/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/8/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/8/2020 | Approved | JUAN VALENZUELA |
| Insulation | 10/8/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/8/2020 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 10/14/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 10/15/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/15/2020 | Approved | JUAN VALENZUELA |
| Shower Pan | 10/15/2020 | Corrections Issued | JUAN VALENZUELA |
| Shower Pan | 10/20/2020 | Approved | JUAN VALENZUELA |
| Final | 11/18/2020 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/18/2020 | Approved | JUAN VALENZUELA |
| Green Building Final | 11/18/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 11/18/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/15/2020 | Approved | JUAN VALENZUELA |
| Final | 12/15/2020 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 12/15/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 12/15/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | JUAN VALENZUELA |