21042 W ROSCOE BLVD 91304

Certificate Information: 21042 W ROSCOE BLVD 91304

Application / Permit
20014-20000-02913
Plan Check / Job No.
B20VN09140
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 21' X 18' CARPORT; ADD 30'-10" X 36'-6" IRREGULAR SHAPE TO AND CONVERT EXISTING REC ROOM TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/26/2020
Issuing Office
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 SELLA BENYAMIN
Corrections Issued 7/20/2020 SELLA BENYAMIN
Building Plans Picked Up 7/21/2020 APPLICANT
Applicant returned to address corrections 7/27/2020 SELLA BENYAMIN
Issued 8/26/2020 APPLICANT
CofO in Progress 12/9/2020 HENRY KIM
Permit Finaled 12/11/2020 JOHN JANSON
CofO Issued 12/11/2020 JOHN JANSON
Permit Finaled 12/11/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/22/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/22/2020 GABRIEL ROBLES
Sewer availability Cleared 7/22/2020 GABRIEL ROBLES
Low Impact Development Cleared 7/31/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/31/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2020 Approved HENRY KIM
Footing/Foundation/Slab 8/28/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 9/1/2020 Approved HENRY KIM
PLUMBING-Rough 9/1/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 9/16/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 9/18/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval HENRY KIM
ELECTRICAL-Rough 9/22/2020 Approved HENRY KIM
HVAC-Rough 9/22/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 9/22/2020 Approved HENRY KIM
BUILDING-Rough-Frame 9/24/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Not Ready for Inspection HENRY KIM
Insulation 9/24/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/24/2020 Approved HENRY KIM
BUILDING-Rough-Frame 9/28/2020 Approved HENRY KIM
Drywall Nailing 9/28/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Approved HENRY KIM
Green Building Rough 9/28/2020 Approved HENRY KIM
Shower Pan 9/29/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/30/2020 Approved HENRY KIM
Underground Mechanical 10/6/2020 Approved HENRY KIM
Sewer 10/8/2020 Approved HENRY KIM
ELECTRICAL-Final 10/30/2020 Corrections Issued HENRY KIM
Final 10/30/2020 Corrections Issued HENRY KIM
Green Building Final 10/30/2020 Corrections Issued HENRY KIM
HVAC-Final 10/30/2020 Corrections Issued HENRY KIM
PLUMBING-Final 10/30/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 10/30/2020 Approved HENRY KIM
ELECTRICAL-Final 11/18/2020 Corrections Issued HENRY KIM
Final 11/18/2020 Not Ready for Inspection HENRY KIM
Green Building Final 11/18/2020 Approved HENRY KIM
HVAC-Final 11/18/2020 Approved HENRY KIM
PLUMBING-Final 11/18/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Approved HENRY KIM
ELECTRICAL-Final 12/9/2020 Approved HENRY KIM
Final 12/9/2020 OK to Issue CofO HENRY KIM