18800 W TULSA ST 91326

Certificate Information: 18800 W TULSA ST 91326

Application / Permit
20014-20000-02911
Plan Check / Job No.
B20VN09136
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6' X 34'-10" FIRST FLOOR ADDITION TO EXPAND AND REMODEL THE (E) KITCHEN, DINING ROOM IN (E) 2-STORY SINGLE FAMILY DWELLING AND 10'-11" X 4' ADDITION TO (E) ATTACHED GARAGE.
Permit Issued
Issued on 10/22/2020
Issuing Office
Current Status
Issued on 10/22/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 SERGIO MUNIZ
Corrections Issued 7/20/2020 SERGIO MUNIZ
Building Plans Picked Up 7/22/2020 APPLICANT
Plan Check Approved 10/7/2020 SERGIO MUNIZ
Issued 10/22/2020 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 9/15/2020 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 9/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Hanson David Walter; Lic. No.: 536128-B P O BOX 280376      NORTHRIDGE, CA 91328
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/16/2020 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/19/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/31/2020 Partial Approval JEFFREY PARD
Green Building Rough 12/31/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/5/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 2/5/2021 Approved JEFFREY PARD
Green Building Rough 2/5/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 2/5/2021 Approved JEFFREY PARD
Deputy Wood Construction 2/9/2021 Approved JEFFREY PARD
Drywall Nailing 2/16/2021 Approved TROY SANDERS
Green Building Rough 2/16/2021 Approved TROY SANDERS
Insulation 2/16/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/16/2021 Approved TROY SANDERS
Gas Test 6/21/2021 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/24/2021 Approved JEFFREY PARD
Final 6/24/2021 Corrections Issued JEFFREY PARD
Green Building Final 6/24/2021 Approved JEFFREY PARD
PLUMBING-Final 6/24/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 6/24/2021 Approved JEFFREY PARD