Work Description
ADDITION ( 23'-3" X 20'-0" ) FOR NEW ATTACHED GARAGE AND CONVERT (E) 20'-5" X 19'-0" ATTACHED GARAGE TO NEW BEDROOM/ BATHROOM AND LAUNDRY ROOM. WORK PER ENGINEER.
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 ROSENDO MEDINA
Corrections Issued 9/28/2020 ROSENDO MEDINA
Applicant returned to address corrections 11/2/2021 ROSENDO MEDINA
Applicant returned to address corrections 4/15/2022 ROSENDO MEDINA
Applicant returned to address corrections 5/10/2022 ROSENDO MEDINA
Applicant returned to address corrections 6/6/2022 ROSENDO MEDINA
Building Plans Picked Up 7/5/2022 APPLICANT
Applicant returned to address corrections 10/13/2022 RAMA DABADGE
Plan Check Approved 11/10/2022 MIROOSH KHACHATOORIAN
Issued 4/6/2023 APPLICANT
CofO in Progress 2/6/2025 STEVEN BACK
Permit Finaled 2/12/2025 JOHN JANSON
CofO Issued 2/12/2025 JOHN JANSON
Permit Finaled 2/12/2025 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 3/3/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/4/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/4/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/30/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/6/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 1530 N DETROIT ST APT 109      LOS ANGELES, CA 90046

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/13/2023 Partial Inspection STEVEN BACK
Deputy Drilled-In Anchors 6/21/2023 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/7/2023 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 7/7/2023 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 7/7/2023 Partial Approval STEVEN BACK
Deputy Reinf. Concrete 7/13/2023 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 8/17/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 8/17/2023 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 8/17/2023 Approved STEVEN BACK
Footing/Foundation/Slab 8/17/2023 Approved STEVEN BACK
PLUMBING-Rough 8/17/2023 Approved STEVEN BACK
Special/Order Compliance 8/17/2023 Partial Inspection JEFFREY HARTLINE
HVAC-Rough 11/1/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 11/20/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Approved STEVEN BACK
Green Building Rough 11/20/2023 Approved STEVEN BACK
Green Building Rough 11/27/2023 Approved STEVEN BACK
Insulation 11/27/2023 Approved STEVEN BACK
Interior/Exterior Lathing 11/27/2023 Partial Approval STEVEN BACK
Drywall Nailing 12/5/2023 Approved MORRIS JACKSON
Shower Pan 12/5/2023 Approved MORRIS JACKSON
Final 10/28/2024 Corrections Issued STEVEN BACK
Green Building Final 10/28/2024 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Approved STEVEN BACK
Smoke Detectors 10/28/2024 Corrections Issued STEVEN BACK
Final 2/6/2025 OK to Issue CofO STEVEN BACK
Green Building Final 2/6/2025 Approved STEVEN BACK
Smoke Detectors 2/6/2025 Approved STEVEN BACK