7441-7443 N RIVERTON AVE 91352
Certificate Information: 7441-7443 N RIVERTON AVE 91352
- Application / Permit
- 20014-20000-02908
- Plan Check / Job No.
- B20VN09126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18' X 15' ADDITION TO AND CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/27/2020
- Issuing Office
- Current Status
- CofO Issued on 3/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/20/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/22/2020 | APPLICANT |
| Plan Check Approved | 9/21/2020 | SELLA BENYAMIN |
| Issued | 10/27/2020 | APPLICANT |
| CofO in Progress | 2/5/2021 | DANIEL DREW |
| CofO Issued | 3/4/2021 | MICHAEL SMITH |
| Permit Finaled | 3/4/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/28/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/28/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | DANIEL DREW |
| Wood Frame | 11/12/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/19/2020 | Approved | DANIEL DREW |
| HVAC-Rough | 11/19/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/19/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/20/2020 | Approved | DANIEL DREW |
| Insulation | 11/24/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/24/2020 | Partial Approval | THOMAS FINNILA |
| Insulation | 11/30/2020 | Not Ready for Inspection | DANIEL ORRANTE |
| PLUMBING-Rough | 11/30/2020 | Approved | DANIEL ORRANTE |
| Wood Frame | 11/30/2020 | Approved | DANIEL ORRANTE |
| Insulation | 12/2/2020 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 12/4/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/7/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 1/20/2021 | Approved | DANIEL DREW |
| Final | 1/20/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 1/20/2021 | Approved | DANIEL DREW |
| HVAC-Final | 1/20/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 1/20/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 1/25/2021 | Approved | DANIEL DREW |
| Final | 1/25/2021 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 1/25/2021 | Approved | DANIEL DREW |
| HVAC-Final | 1/25/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 1/25/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 1/25/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 1/25/2021 | Approved | DANIEL DREW |
| Final | 1/29/2021 | Partial Inspection | BEAU COLLINS |
| Final | 2/5/2021 | OK to Issue CofO | DANIEL DREW |