8107 S BLERIOT AVE 90045

Certificate Information: 8107 S BLERIOT AVE 90045

Application / Permit
20014-20000-02906
Plan Check / Job No.
B20VN09121
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16'-11" X 19'-3" IRREGULAR SHAPED ADDITION AT FRONT AND 10' X 13'-8" ADDITION AT REAR AND REMODEL (E) SFD FOR (N) BEDROOMS, BATHROOMS, CLOSETS, LIVING ROOM, DINING ROOM AND KITCHEN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/4/2021
Issuing Office
Current Status
CofO Issued on 4/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 RAPHAEL ROSAS
Corrections Issued 7/27/2020 RAPHAEL ROSAS
Applicant returned to address corrections 8/28/2020 RAPHAEL ROSAS
Applicant returned to address corrections 9/15/2020 RAPHAEL ROSAS
Issued 5/4/2021 APPLICANT
CofO in Progress 4/18/2022 BOBBY KEY
Permit Finaled 4/20/2022 DANIEL ORRANTE
CofO Issued 4/20/2022 DANIEL ORRANTE
Permit Finaled 4/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/18/2020 NIKTA MOUSAVI
Sewer availability Cleared 8/18/2020 NIKTA MOUSAVI
Low Impact Development Cleared 2/23/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/27/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2021 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 5/12/2021 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 5/14/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 5/27/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 5/27/2021 Not Ready for Inspection BRENDAN LOONEY
Insulation 5/28/2021 Partial Approval BRENDAN LOONEY
Pre-Inspection 6/30/2021 Partial Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/14/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 9/14/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 9/14/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 9/14/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/21/2021 Approved BRENDAN LOONEY
HVAC-Rough 9/21/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 9/21/2021 Approved BRENDAN LOONEY
Wood Frame 9/21/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 9/29/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 10/6/2021 Conditional Approval BRENDAN LOONEY
Insulation 10/15/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 10/26/2021 Approved BOBBY KEY
Green Building Rough 10/26/2021 Approved BOBBY KEY
Insulation 10/26/2021 Approved BOBBY KEY
Drywall Nailing 11/1/2021 Approved BOBBY KEY
Shower Pan 11/1/2021 Approved BOBBY KEY
Interior/Exterior Lathing 11/5/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/2/2021 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 12/7/2021 Approved BOBBY KEY
Final 1/28/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/28/2022 Approved BOBBY KEY
Green Building Final 1/28/2022 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 1/28/2022 Approved BOBBY KEY
Gas Test 2/4/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 2/7/2022 Approved ANDREW NAVE
PLUMBING-Final 2/7/2022 Corrections Issued ANDREW NAVE
Green Building Final 2/11/2022 Approved BOBBY KEY
HVAC-Final 2/11/2022 Approved BOBBY KEY
PLUMBING-Final 2/11/2022 Approved BOBBY KEY
Final 4/18/2022 OK to Issue CofO BOBBY KEY