19542 W HAMLIN ST 91335

Certificate Information: 19542 W HAMLIN ST 91335

Application / Permit
20014-20000-02886
Plan Check / Job No.
B20VN09090
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. (20'-0"x25'-6") ALL WORKS PER WFPP per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 MOHAMMAD ESMAILI
Corrections Issued 7/18/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 4/9/2021 MOHAMMAD ESMAILI
Issued 4/9/2021 APPLICANT
CofO in Progress 1/31/2022 STEVEN BACK
Permit Finaled 2/1/2022 JOHN JANSON
CofO Issued 2/1/2022 JOHN JANSON
Permit Finaled 2/1/2022 JOHN JANSON

Permit Application Clearance Information

Construction within easement Cleared 1/20/2021 RIDWAN HARDY
Address approval Cleared 1/22/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/25/2021 ADRIAN CASTRO
Sewer availability Cleared 1/25/2021 ADRIAN CASTRO
ZI Cleared 2/24/2021 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2021 Approved RONALD COWAN
Footing/Foundation/Slab 6/21/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 7/12/2021 Approved HENRY KIM
ELECTRICAL-Rough 8/11/2021 Not Ready for Inspection PETER FOLLING
HVAC-Rough 8/11/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 8/11/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 8/25/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Corrections Issued HENRY KIM
HVAC-Rough 8/25/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 8/25/2021 Corrections Issued HENRY KIM
Sewer 8/25/2021 Approved HENRY KIM
Underground Mechanical 8/25/2021 Approved HENRY KIM
Insulation 9/8/2021 Partial Inspection RYAN SALAZAR
ELECTRICAL-Rough 9/13/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Corrections Issued HENRY KIM
HVAC-Rough 9/13/2021 Not Ready for Inspection HENRY KIM
Insulation 9/13/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 9/13/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Corrections Issued HENRY KIM
Green Building Rough 9/15/2021 Not Ready for Inspection HENRY KIM
Insulation 9/15/2021 Partial Approval HENRY KIM
PLUMBING-Rough 9/15/2021 Approved HENRY KIM
Pre-Inspection 9/15/2021 Partial Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Corrections Issued HENRY KIM
Insulation 9/23/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Not Ready for Inspection HENRY KIM
Pre-Inspection 9/27/2021 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 10/1/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Approved HENRY KIM
Shower Pan 10/1/2021 Approved HENRY KIM
Interior/Exterior Lathing 10/8/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/20/2022 Approved STEVEN BACK
Final 1/20/2022 Corrections Issued STEVEN BACK
Green Building Final 1/20/2022 Approved STEVEN BACK
Green Building Rough 1/20/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 1/20/2022 Approved STEVEN BACK
Final 1/31/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved STEVEN BACK