16740 W OTSEGO ST 91436

Certificate Information: 16740 W OTSEGO ST 91436

Application / Permit
20014-20000-02879
Plan Check / Job No.
B20VN09054
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 50' X 43' 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ATTACHED 28'-6" X 14' PATIO DECK. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofO Corrected on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 SERGIO MUNIZ
Corrections Issued 8/5/2020 SERGIO MUNIZ
Quality Review Completed 9/8/2020 OMID HEDAYAT
Applicant returned to address corrections 3/9/2021 SERGIO MUNIZ
Applicant returned to address corrections 3/24/2021 SERGIO MUNIZ
Applicant returned to address corrections 4/6/2021 SERGIO MUNIZ
Applicant returned to address corrections 5/13/2021 SERGIO MUNIZ
Plan Check Approved 6/8/2021 SERGIO MUNIZ
Issued 6/10/2021 APPLICANT
Building Plans Picked Up 6/14/2021 APPLICANT
CofO in Progress 7/27/2022 VINCENT HANLEY
CofO Issued-Status Void 8/30/2022 MICHAEL SMITH
Permit Finaled-Status Void 8/30/2022 MICHAEL SMITH
Re-Activate Permit 9/3/2022 MICHAEL SMITH
CofO Corrected 4/4/2023 JOHN JANSON
Permit Finaled 4/4/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2020 ADRIAN CASTRO
Permit Cleared 8/19/2020 ADRIAN CASTRO
Sewer availability Cleared 8/19/2020 ADRIAN CASTRO
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Low Impact Development Cleared 1/26/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/26/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG

Contact Information

Contractor M I G Construction Services Inc; Lic. No.: 384877-B 15250 VENTURA BLVD STE 601      SHERMAN OAKS, CA 91403
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2021 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/15/2021 Partial Approval STEPHANIE SWANSON
Pre-Inspection 6/15/2021 Partial Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/25/2021 Corrections Issued MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/28/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 6/28/2021 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval RONALD COWAN
Deputy Drilled-In Anchors 10/1/2021 Approved RONALD COWAN
Deputy Wood Construction 10/1/2021 Approved RONALD COWAN
HVAC-Rough 10/7/2021 Approved RONALD COWAN
PLUMBING-Rough 10/13/2021 Approved RONALD COWAN
Deputy Wood Construction 10/29/2021 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 11/4/2021 Approved RONALD COWAN
Interior/Exterior Lathing 11/4/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 11/8/2021 Approved RONALD COWAN
Green Building Rough 11/8/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 11/8/2021 Approved RONALD COWAN
Drywall Nailing 12/2/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/2/2021 Approved SEAN HAUPT
Gas Test 3/15/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 5/6/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 5/20/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 5/20/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 5/20/2022 Corrections Issued VINCENT HANLEY
Final 5/23/2022 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 5/23/2022 Approved PETER FOLLING
Green Building Final 5/23/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved PETER FOLLING
Service/Power Release 5/23/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 5/23/2022 Approved PETER FOLLING
ELECTRICAL-Final 7/8/2022 Approved VINCENT HANLEY
Final 7/8/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 7/8/2022 Approved VINCENT HANLEY
PLUMBING-Final 7/8/2022 Approved VINCENT HANLEY
Service/Power Release 7/8/2022 Not Ready for Inspection VINCENT HANLEY
Final 7/27/2022 OK to Issue CofO VINCENT HANLEY
Service/Power Release 7/27/2022 Approved VINCENT HANLEY
Special/Order Compliance 9/8/2022 Corrections Issued VINCENT HANLEY