4528 W COCKERHAM DR 90027

Certificate Information: 4528 W COCKERHAM DR 90027

Application / Permit
20014-20000-02868
Plan Check / Job No.
B20VN09032
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-0" X 46'-8" ADDITION FOR NEW ATTACHED TRELLIS AND 8'-6" X 6'-0" BATHROOM (EXTERIOR ACCESS ONLY) WITHIN PER ENGINEER
Permit Issued
Issued on 5/16/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 JEROME MAGAT PALMA
Corrections Issued 7/20/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 1/22/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 4/26/2021 JEROME MAGAT PALMA
Plan Check Approved 5/14/2021 JEROME MAGAT PALMA
Issued 5/16/2021 APPLICANT
Building Plans Picked Up 5/19/2021 APPLICANT
CofO in Progress 5/5/2022 JOSEPH MCGARRY
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/26/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/27/2021 JEANIE LAM
Grading Pre-Inspection Cleared 5/14/2021 JEROME MAGAT PALMA

Contact Information

Contractor Warner Douglas Wade; Lic. No.: 497676-B 726 CALLE CARDO      THOUSAND OAKS, CA 91360
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/28/2021 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/22/2021 Partial Approval JOSEPH MCGARRY
Green Building Rough 9/22/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 11/17/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 1/26/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 1/26/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/26/2022 Approved JOSEPH MCGARRY
Special/Order Compliance 1/26/2022 Partial Approval JOSEPH MCGARRY
Final 4/5/2022 Corrections Issued ARTHUR SARGSYAN
Green Building Final 4/5/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 4/5/2022 Approved ARTHUR SARGSYAN
Final 5/5/2022 OK to Issue CofO JOSEPH MCGARRY
Special/Order Compliance 5/18/2022 Approved JOSEPH MCGARRY