3612 E BALDWIN ST 90031

Certificate Information: 3612 E BALDWIN ST 90031

Application / Permit
20014-20000-02867
Plan Check / Job No.
B20VN09031
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (16'0" X 13'-8") SECOND STORY MASTER BEDROOM AND BATH TO (E) 2-STORY SINGLE FAMILY DWELLING WITH CARPORT BELOW. WORK PER ENGINEER.
Permit Issued
Issued on 12/8/2020
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 TROY DEGUZMAN
Corrections Issued 7/18/2020 TROY DEGUZMAN
Building Plans Picked Up 7/23/2020 APPLICANT
Plan Check Approved 12/8/2020 TROY DEGUZMAN
Issued 12/8/2020 APPLICANT
CofO in Progress 4/20/2022 OSVALDO PARAMO
CofO in Progress 4/20/2022 OSVALDO PARAMO
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2020 WALLIE JONG
Sewer availability Cleared 8/5/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/10/2020 WALLIE JONG
Grading Pre-Inspection Cleared 8/27/2020 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2021 Partial Approval OSVALDO PARAMO
Deputy Steel/Welding 3/19/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 6/18/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/18/2021 Approved OSVALDO PARAMO
Deputy Reinf. Concrete 6/23/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 8/5/2021 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Corrections Issued COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 10/4/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/13/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 10/13/2021 Partial Approval OSVALDO PARAMO
Green Building Rough 10/13/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 10/13/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 10/15/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 10/15/2021 Approved OSVALDO PARAMO
Wood Frame 10/15/2021 Approved OSVALDO PARAMO
HVAC-Rough 10/18/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/18/2021 Partial Approval OSVALDO PARAMO
Insulation 10/20/2021 Approved OSVALDO PARAMO
Drywall Nailing 10/25/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/1/2021 Approved OSVALDO PARAMO
Final 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
Final 12/13/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 12/13/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 12/13/2021 Approved OSVALDO PARAMO
Final 4/19/2022 OK to Issue CofO OSVALDO PARAMO