7560-7562 N CHAMINADE AVE 91304
Certificate Information: 7560-7562 N CHAMINADE AVE 91304
- Application / Permit
- 20014-20000-02849
- Plan Check / Job No.
- B20VN08980
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 7'-5" X 7'-7" (56 SQFT) ADDITION TO REAR AND 18'-5" X 4' (74 SQFT) ADDITION TO WEST SIDE OF (E) ATTACHED GARAGE AND CONVERT (E) ATTACHED GARAGE (396 SQFT) & CONVERT (E) 3''-10" X 7'-7" (29 SQFT) PORTION OF (E) SFD TO ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 5/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 7/22/2020 | APPLICANT |
| Plan Check Approved | 8/14/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 5/3/2021 | DAVID STEPANYAN |
| Permit Finaled | 5/12/2021 | JOHN JANSON |
| CofO Issued | 5/12/2021 | JOHN JANSON |
| Permit Finaled | 5/12/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 8/4/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/22/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/22/2020 | Partial Approval | DAVID STEPANYAN |
| Sewer | 10/22/2020 | Approved | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 11/12/2020 | Conditional Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/24/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 12/24/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 12/24/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 1/7/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 1/7/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 1/7/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 1/7/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 1/7/2021 | Approved | DAVID STEPANYAN |
| Insulation | 1/11/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 1/19/2021 | Approved | MARK JOHNSON |
| Final | 3/26/2021 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 3/26/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/26/2021 | Approved | STEVEN BACK |
| Final | 4/21/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 5/3/2021 | Approved | DAVID STEPANYAN |
| Final | 5/3/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Gas Test | 5/3/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 5/3/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 5/3/2021 | Approved | DAVID STEPANYAN |