7732 N CHIMINEAS AVE 91335
Certificate Information: 7732 N CHIMINEAS AVE 91335
- Application / Permit
- 20014-20000-02838
- Plan Check / Job No.
- B20VN08957
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 10' x 10'-11" to add bathroom to single-family dwelling per engineer
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofO Issued on 3/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | ANGELICA DAVE |
| Corrections Issued | 7/21/2020 | ANGELICA DAVE |
| Plan Check Approved | 8/24/2020 | ANGELICA MARTINEZ |
| Issued | 8/25/2020 | APPLICANT |
| CofO in Progress | 2/26/2021 | VINCENT HANLEY |
| CofO Issued | 3/1/2021 | MICHAEL SMITH |
| Permit Finaled | 3/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/11/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/14/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 9/14/2020 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 9/24/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/23/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 11/25/2020 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/25/2020 | Approved | VINCENT HANLEY |
| Gas Test | 11/25/2020 | Partial Approval | VINCENT HANLEY |
| Insulation | 11/25/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/25/2020 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/25/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 11/25/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 12/7/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/9/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/26/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/26/2021 | Approved | VINCENT HANLEY |
| Final | 2/26/2021 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 2/26/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/26/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/26/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/26/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/26/2021 | Approved | VINCENT HANLEY |