7732 N CHIMINEAS AVE 91335

Certificate Information: 7732 N CHIMINEAS AVE 91335

Application / Permit
20014-20000-02838
Plan Check / Job No.
B20VN08957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 10' x 10'-11" to add bathroom to single-family dwelling per engineer
Permit Issued
Issued on 8/25/2020
Issuing Office
Current Status
CofO Issued on 3/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 ANGELICA DAVE
Corrections Issued 7/21/2020 ANGELICA DAVE
Plan Check Approved 8/24/2020 ANGELICA MARTINEZ
Issued 8/25/2020 APPLICANT
CofO in Progress 2/26/2021 VINCENT HANLEY
CofO Issued 3/1/2021 MICHAEL SMITH
Permit Finaled 3/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/11/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/14/2020 Partial Approval VINCENT HANLEY
Sewer 9/14/2020 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/22/2020 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/24/2020 Approved HENRY KIM
Footing/Foundation/Slab 9/24/2020 Approved HENRY KIM
ELECTRICAL-Rough 10/23/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Corrections Issued HENRY KIM
ELECTRICAL-Final 11/25/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/25/2020 Approved VINCENT HANLEY
Gas Test 11/25/2020 Partial Approval VINCENT HANLEY
Insulation 11/25/2020 Approved VINCENT HANLEY
PLUMBING-Final 11/25/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/25/2020 Approved VINCENT HANLEY
Wood Frame 11/25/2020 Approved VINCENT HANLEY
Drywall Nailing 12/7/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/9/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/26/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 2/26/2021 Approved VINCENT HANLEY
Final 2/26/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 2/26/2021 Approved VINCENT HANLEY
Green Building Rough 2/26/2021 Approved VINCENT HANLEY
HVAC-Final 2/26/2021 Approved VINCENT HANLEY
PLUMBING-Final 2/26/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/26/2021 Approved VINCENT HANLEY