10867 N SHARP AVE 91345
Certificate Information: 10867 N SHARP AVE 91345
- Application / Permit
- 20014-20000-02804
- Plan Check / Job No.
- B20VN08894
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 26'6" X 14' ATTACHED REAR ENCLOSED PATIO , NEW 25'6" X 14' ADDITON TO (E) SFD FOR NEW KITCHEN AND NEW 14'3" X 10' ADDITION TO CREATE NEW BATHROOM , CLOSET AND ENLARGE THE BEDROOM , ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Valley
- Current Status
- Issued on 1/11/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2020 | PINANK PATEL |
| Corrections Issued | 7/31/2020 | PINANK PATEL |
| Applicant returned to address corrections | 10/9/2020 | RARES BODEA |
| No Progress | 10/9/2020 | RARES BODEA |
| Applicant returned to address corrections | 1/7/2021 | ALFRED RAMIREZ |
| Issued | 1/11/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 12/22/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/7/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/20/2021 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 11/3/2021 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/3/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 11/3/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 11/3/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 11/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/8/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 4/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/8/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/18/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/18/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 5/3/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 5/3/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/5/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| Final | 10/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 10/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 10/14/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/14/2022 | Approved | JENNIFER RABUCHIN |