7540 N TAMPA AVE 91335

Certificate Information: 7540 N TAMPA AVE 91335

Application / Permit
20014-20000-02801
Plan Check / Job No.
B20VN08888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
COVERT (E) 20' X 28' DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADD 5' X 23'-5" COVERED PORCH. ALL WORK PER WFPP.
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 RAPHAEL ROSAS
Corrections Issued 7/10/2020 RAPHAEL ROSAS
Plan Check Approved 10/30/2020 RAPHAEL ROSAS
Issued 11/10/2020 APPLICANT
CofO in Progress 11/2/2022 JEFFREY BULL
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/22/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 9/28/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 12/7/2021 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/16/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/16/2021 Approved VINCENT HANLEY
PLUMBING-Rough 12/16/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/12/2022 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/12/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 4/12/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/12/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 5/23/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/23/2022 Approved VINCENT HANLEY
Green Building Rough 5/23/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/23/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/23/2022 Approved VINCENT HANLEY
Insulation 6/24/2022 Approved DAVID SANDOVAL
Drywall Nailing 7/12/2022 Approved MORRIS JACKSON
Final 9/26/2022 Corrections Issued JEFFREY BULL
Green Building Final 9/26/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 9/26/2022 Approved JEFFREY BULL
Final 10/11/2022 Corrections Issued STEVEN BACK
Green Building Final 10/11/2022 Approved STEVEN BACK
Final 10/27/2022 OK to Issue CofO JEFFREY BULL