10955 N LEOLANG AVE 91040
Certificate Information: 10955 N LEOLANG AVE 91040
- Application / Permit
- 20014-20000-02793
- Plan Check / Job No.
- B20VN08864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20'-2" X 12'-11" ADDITION TO ENLARGE BEDROOM AND ADD CLOSET AND BATHROOM
- Permit Issued
- Issued on 8/18/2020
- Issuing Office
- Current Status
- CofO Issued on 8/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/8/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/30/2020 | JEROME MAGAT PALMA |
| Issued | 8/18/2020 | APPLICANT |
| CofO in Progress | 4/29/2021 | MATTHEW NELSON |
| CofO Issued | 8/7/2021 | MICHAEL SMITH |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/15/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 7/21/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/12/2020 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/16/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/30/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/30/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 11/30/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/30/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 11/30/2020 | Approved | MATTHEW NELSON |
| Insulation | 12/3/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/3/2020 | Approved | MATTHEW NELSON |
| Shower Pan | 12/7/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/11/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/16/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Pre-Inspection | 1/21/2021 | Approved | MATTHEW NELSON |
| Final | 4/29/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 4/29/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/29/2021 | Approved | MATTHEW NELSON |