6941 N GARDEN GROVE AVE 91335

Certificate Information: 6941 N GARDEN GROVE AVE 91335

Application / Permit
20014-20000-02787
Plan Check / Job No.
B20VN08840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (13'-2" x 9' ) TO (E) SFD FOR NEW BATHROOM AND EXTEND BEDROOM. WORK PER WFPP.
Permit Issued
Issued on 9/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/4/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 ROSENDO MEDINA
Corrections Issued 7/11/2020 ROSENDO MEDINA
Plan Check Approved 9/2/2020 ROSENDO MEDINA
Issued 9/2/2020 APPLICANT
CofO in Progress 3/12/2021 VINCENT HANLEY
Permit Finaled 3/23/2021 MICHAEL SMITH
CofO Issued 3/23/2021 MICHAEL SMITH
Permit Finaled 3/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/2/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/2/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/5/2020 Partial Approval VINCENT HANLEY
Green Building Rough 11/5/2020 Partial Approval VINCENT HANLEY
Insulation 11/5/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/17/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/17/2020 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 11/17/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/17/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/20/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/20/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Approved VINCENT HANLEY
Green Building Rough 11/20/2020 Approved VINCENT HANLEY
PLUMBING-Rough 11/20/2020 Approved VINCENT HANLEY
Insulation 11/24/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/24/2020 Not Ready for Inspection VINCENT HANLEY
Shower Pan 11/24/2020 Approved VINCENT HANLEY
Drywall Nailing 12/1/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/1/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/8/2021 Approved VINCENT HANLEY
Final 3/8/2021 Corrections Issued VINCENT HANLEY
Green Building Final 3/8/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 3/8/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 3/12/2021 Approved VINCENT HANLEY
Final 3/12/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/12/2021 Approved VINCENT HANLEY
PLUMBING-Final 3/12/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved VINCENT HANLEY