14833 1/2 W TUBA ST 91345
Certificate Information: 14833 1/2 W TUBA ST 91345
- Application / Permit
- 20014-20000-02786
- Plan Check / Job No.
- B20VN08839
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2' X 25' IRREGULAR SHAPED ADDITION TO FIRST FLOOR; ADD 20' X 25' SECOND FLOOR TO GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT; REMOVE 2' X 18' PORTION OF GARAGE
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Current Status
- CofO Issued on 10/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/27/2020 | SELLA BENYAMIN |
| Quality Review Completed | 7/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| Plan Check Approved | 9/2/2020 | SELLA BENYAMIN |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 8/30/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 10/19/2021 | MICHAEL SMITH |
| CofO Issued | 10/19/2021 | MICHAEL SMITH |
| Permit Finaled | 10/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/21/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 8/27/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 8/28/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/1/2020 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/17/2020 | Conditional Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 12/21/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/11/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/17/2021 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 3/17/2021 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 3/17/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/17/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 3/17/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Partial Inspection | MICHAEL TEMPLE |
| Wood Frame | 3/23/2021 | Corrections Issued | DANIEL ORRANTE |
| HVAC-Rough | 3/26/2021 | Corrections Issued | MICHAEL TEMPLE |
| Wood Frame | 3/26/2021 | Corrections Issued | MICHAEL TEMPLE |
| Wood Frame | 4/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 4/30/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 5/6/2021 | Approved | MORRIS JACKSON |
| Pre-Inspection | 5/6/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/18/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/8/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/13/2021 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/19/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/24/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/24/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/24/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/24/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/24/2021 | Approved | JENNIFER RABUCHIN |