14833 1/2 W TUBA ST 91345

Certificate Information: 14833 1/2 W TUBA ST 91345

Application / Permit
20014-20000-02786
Plan Check / Job No.
B20VN08839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2' X 25' IRREGULAR SHAPED ADDITION TO FIRST FLOOR; ADD 20' X 25' SECOND FLOOR TO GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT; REMOVE 2' X 18' PORTION OF GARAGE
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SELLA BENYAMIN
Corrections Issued 7/27/2020 SELLA BENYAMIN
Quality Review Completed 7/28/2020 STEVEN KIM
Building Plans Picked Up 8/20/2020 APPLICANT
Plan Check Approved 9/2/2020 SELLA BENYAMIN
Issued 9/2/2020 APPLICANT
CofO in Progress 8/30/2021 JENNIFER RABUCHIN
Permit Finaled 10/19/2021 MICHAEL SMITH
CofO Issued 10/19/2021 MICHAEL SMITH
Permit Finaled 10/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/21/2020 ADRIAN CASTRO
Sewer availability Cleared 8/21/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 8/27/2020 ADRIAN CASTRO
Construction near power lines Cleared 8/28/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/1/2020 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/17/2020 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 12/21/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/2/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 3/11/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/17/2021 Partial Approval JENNIFER RABUCHIN
Gas Test 3/17/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 3/17/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/17/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 3/17/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Partial Inspection MICHAEL TEMPLE
Wood Frame 3/23/2021 Corrections Issued DANIEL ORRANTE
HVAC-Rough 3/26/2021 Corrections Issued MICHAEL TEMPLE
Wood Frame 3/26/2021 Corrections Issued MICHAEL TEMPLE
Wood Frame 4/22/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/30/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/30/2021 Approved JENNIFER RABUCHIN
Green Building Rough 4/30/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 4/30/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 5/6/2021 Approved MORRIS JACKSON
Pre-Inspection 5/6/2021 Partial Inspection ALIZAH MAYAGOITIA
Drywall Nailing 5/18/2021 Approved JENNIFER RABUCHIN
Shower Pan 7/8/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/13/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 8/19/2021 Corrections Issued JENNIFER RABUCHIN
Final 8/19/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/19/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 8/19/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/19/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/24/2021 Approved JENNIFER RABUCHIN
Final 8/24/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/24/2021 Approved JENNIFER RABUCHIN
HVAC-Final 8/24/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/24/2021 Approved JENNIFER RABUCHIN