15956 W VOSE ST 91406

Certificate Information: 15956 W VOSE ST 91406

Application / Permit
20014-20000-02782
Plan Check / Job No.
B20VN08836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CHANGE OF USE FROM EX ACCESSORY LIVING QUARTERS TO ACCESSORY DWELLING UNIT W/ 20'7"X9' IRR SHAPED ADDITION PER ORD #186,481. DESIGN PER ENGR.
Permit Issued
Issued on 1/12/2021
Issuing Office
Valley
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 HAYATO TSUCHIYA
Corrections Issued 7/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/7/2021 HAYATO TSUCHIYA
Plan Check Approved 1/12/2021 HAYATO TSUCHIYA
Issued 1/12/2021 APPLICANT
CofO in Progress 10/12/2021 JACK KARGODORIAN
Permit Finaled 10/13/2021 MICHAEL SMITH
CofO Issued 10/13/2021 MICHAEL SMITH
Permit Finaled 10/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/4/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/4/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/9/2020 GUILLERMO PETRA
Sewer availability Cleared 11/9/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/4/2021 Partial Approval ARTHUR SARGSYAN
Underground Mechanical 3/4/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 3/12/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 3/12/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/21/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval ARTHUR SARGSYAN
Gas Test 4/21/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/21/2021 Approved ARTHUR SARGSYAN
Wood Frame 4/21/2021 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/29/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Approved ARTHUR SARGSYAN
Gas Test 4/29/2021 Approved ARTHUR SARGSYAN
Green Building Rough 4/29/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 4/29/2021 Approved ARTHUR SARGSYAN
Insulation 5/10/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/10/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 5/17/2021 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/27/2021 Not Ready for Inspection JACK KARGODORIAN
Final 9/27/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 9/27/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 9/27/2021 Approved JACK KARGODORIAN
PLUMBING-Final 9/27/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/27/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 9/30/2021 Approved JACK KARGODORIAN
Final 9/30/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 9/30/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 9/30/2021 Approved JACK KARGODORIAN
PLUMBING-Final 9/30/2021 Approved JACK KARGODORIAN
Final 10/12/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 10/12/2021 Approved JACK KARGODORIAN