5717 N MCDONIE AVE 91367

Certificate Information: 5717 N MCDONIE AVE 91367

Application / Permit
20014-20000-02772
Plan Check / Job No.
B20VN08817
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED REC RM ADDITION (13'7"X9'4") TO EX 1-STORY SFD W/ ATT 1-CAR GARAGE/STORAGE RM WITHIN EX OPEN COMPACT STALL & CONVERT EX STORAGE AREA (5'1"X7'4") WITHIN THE GARAGE INTO POR OF NEW REC RM. ALL WORK PER ENGR DESIGN. THE REC RM HAS NO INTERNAL ACCESS FROM THE HOUSE & GARAGE. AND NO PLUMBING FIXTURES. SEE COMMENTS.
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 HAYATO TSUCHIYA
Corrections Issued 7/10/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 9/10/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/6/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/28/2020 HAYATO TSUCHIYA
Plan Check Approved 12/9/2020 HAYATO TSUCHIYA
Issued 12/10/2020 APPLICANT
CofO in Progress 3/17/2021 HENRY KIM
Permit Finaled 9/22/2022 JOHN JANSON
CofO Issued 9/22/2022 JOHN JANSON
Permit Finaled 9/22/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/12/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 11/12/2020 GABRIEL ROBLES
Grading Pre-Inspection Cleared 12/3/2020 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2020 Approved HENRY KIM
Footing/Foundation/Slab 1/19/2021 Approved HENRY KIM
BUILDING-Rough-Frame 2/10/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/19/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Approved HENRY KIM
BUILDING-Rough-Frame 2/23/2021 Approved HENRY KIM
ELECTRICAL-Rough 2/23/2021 Approved HENRY KIM
Green Building Rough 2/23/2021 Approved HENRY KIM
Insulation 2/23/2021 Approved HENRY KIM
Interior/Exterior Lathing 2/23/2021 Approved HENRY KIM
Drywall Nailing 3/1/2021 Partial Approval HENRY KIM
Drywall Nailing 3/3/2021 Approved HENRY KIM
ELECTRICAL-Final 3/12/2021 Corrections Issued HENRY KIM
Final 3/12/2021 Not Ready for Inspection HENRY KIM
Green Building Final 3/12/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved HENRY KIM
Smoke Detectors 3/12/2021 Approved HENRY KIM
ELECTRICAL-Final 3/17/2021 Approved HENRY KIM
Final 3/17/2021 OK to Issue CofO HENRY KIM