12335 W LULL ST 91605

Certificate Information: 12335 W LULL ST 91605

Application / Permit
20014-20000-02758
Plan Check / Job No.
B20VN08780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 34'5" X 48'6" IRR. SHAPE ADU TO (E) DETACHED GARAGE. ALL WORK PER ENGINEER.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 5/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 PINANK PATEL
Corrections Issued 7/27/2020 PINANK PATEL
Quality Review Completed 7/28/2020 STEVEN KIM
Plan Check Approved 2/26/2021 PINANK PATEL
Issued 3/15/2021 APPLICANT
Building Plans Picked Up 3/26/2021 APPLICANT
CofO in Progress 2/24/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 5/25/2022 MICHAEL SMITH
CofO Issued 5/25/2022 MICHAEL SMITH
Permit Finaled 5/25/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 10/28/2020 RIDWAN HARDY
Address approval Cleared 11/25/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 1/5/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/8/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/18/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2021 Partial Approval JOHN HAYES
METHANE-Barrier 3/18/2021 Approved JOHN HAYES
METHANE-Subgrade 3/18/2021 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/19/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/1/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 4/1/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/5/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 4/7/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 5/26/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/26/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/26/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/26/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 5/27/2021 Approved JOHN HAYES
METHANE-Rough 5/27/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 5/27/2021 Approved JOHN HAYES
Insulation 6/2/2021 Approved ALAN MORELOS
Drywall Nailing 6/4/2021 Approved MORRIS JACKSON
Green Building Rough 6/4/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/9/2021 Approved MORRIS JACKSON
Shower Pan 6/9/2021 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 6/28/2021 Approved MORRIS JACKSON
Shower Pan 6/28/2021 Approved MORRIS JACKSON
Gas Test 8/19/2021 Not Ready for Inspection JOHN HAYES
Sewer 8/19/2021 Not Ready for Inspection JOHN HAYES
Gas Test 8/20/2021 Partial Approval JAVIER RAMOS JR
Sewer 8/20/2021 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Not Ready GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Not Ready MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
Final 1/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/7/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 1/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
METHANE-Final 1/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
METHANE-Rough 1/7/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 1/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/1/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 2/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
METHANE-Final 2/1/2022 Approved CHRISTOPHER DELLEFIELD
METHANE-Rough 2/1/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/1/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 2/1/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/10/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 2/10/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/24/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/24/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 2/24/2022 Approved CHRISTOPHER DELLEFIELD