12419 W STAGG ST 91605

Certificate Information: 12419 W STAGG ST 91605

Application / Permit
20014-20000-02741
Plan Check / Job No.
B20VN08727
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (37'-5"x 31'-4") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d) ATTACHED TO (E) DETACHED 2-CAR GARAGE. WORK PER ENGINEER.
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 1/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 TROY DEGUZMAN
Corrections Issued 7/29/2020 TROY DEGUZMAN
Building Plans Picked Up 7/31/2020 APPLICANT
Plan Check Approved 3/3/2021 TROY DEGUZMAN
Issued 3/3/2021 APPLICANT
CofO in Progress 12/14/2021 CHRISTOPHER DELLEFIELD
Permit Finaled 1/18/2022 MICHAEL SMITH
CofO Issued 1/18/2022 MICHAEL SMITH
Permit Finaled 1/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction within easement Cleared 10/30/2020 RIDWAN HARDY
Address approval Cleared 11/13/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/26/2021 GUILLERMO PETRA
Low Impact Development Cleared 2/10/2021 SARAH YOUSSEF
Sewer availability Cleared 2/10/2021 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 2/17/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/1/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/9/2021 Corrections Issued JOHN HAYES
Pre-Inspection 4/9/2021 Not Ready for Inspection JOHN HAYES
Underground Mechanical 4/9/2021 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 4/12/2021 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 4/14/2021 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/15/2021 Approved JOHN HAYES
Footing/Foundation/Slab 4/15/2021 Approved JOHN HAYES
Underground Mechanical 4/15/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Partial Approval DAVID MATSON
HVAC-Rough 4/29/2021 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 4/29/2021 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 5/4/2021 Partial Approval JOHN HAYES
Green Building Rough 5/4/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/4/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/4/2021 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 5/4/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/6/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Approved JOHN HAYES
Green Building Rough 5/6/2021 Approved JOHN HAYES
Interior/Exterior Lathing 5/6/2021 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 5/6/2021 Approved JOHN HAYES
Deputy Wood Construction 5/10/2021 Conditional Approval JOHN HAYES
Drywall Nailing 5/11/2021 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/11/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/11/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 5/11/2021 Partial Inspection MORRIS JACKSON
Interior/Exterior Lathing 5/19/2021 Approved JOHN HAYES
Service/Power Release 5/19/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Final 6/21/2021 Not Ready for Inspection JOHN HAYES
Final 6/21/2021 Not Ready for Inspection JOHN HAYES
Gas Test 6/21/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 6/21/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 6/21/2021 Not Ready for Inspection JOHN HAYES
Final 8/16/2021 No Access for Inspection WILLIAM KUEHN
Green Building Final 8/16/2021 No Access for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Not Ready WILLIAM KUEHN
Smoke Detectors 8/16/2021 No Access for Inspection WILLIAM KUEHN
ELECTRICAL-Final 9/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 9/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Gas Test 9/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 9/22/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 9/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 9/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 9/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 9/22/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/7/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Gas Test 10/7/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/7/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/7/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/14/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/13/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD