5710 N CEDROS AVE 91411

Certificate Information: 5710 N CEDROS AVE 91411

Application / Permit
20014-20000-02734
Plan Check / Job No.
B20VN08703
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 9/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 JEROME MAGAT PALMA
Corrections Issued 7/12/2020 JEROME MAGAT PALMA
Plan Check Approved 7/21/2020 JEROME MAGAT PALMA
Issued 9/24/2024 APPLICANT
CofO in Progress 8/22/2025 RYAN SALAZAR
CofO Issued 8/27/2025 RUBEN SALAS
Permit Finaled 8/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/17/2020 ADRIAN CASTRO
Sewer availability Cleared 7/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/21/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/12/2024 Conditional Approval RAUL OLAGI
Deputy Drilled-In Anchors 11/25/2024 Conditional Approval RAUL OLAGI
PLUMBING-Rough 11/27/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/30/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 12/30/2024 Approved RYAN SALAZAR
Green Building Rough 12/30/2024 Approved RYAN SALAZAR
PLUMBING-Rough 12/30/2024 Approved RYAN SALAZAR
HVAC-Rough 1/3/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/3/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 1/3/2025 Partial Approval JENNIFER RABUCHIN
Insulation 1/7/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/7/2025 Partial Approval RYAN SALAZAR
Rough-Elec/Plmb/HVAC 1/7/2025 Approved RYAN SALAZAR
Drywall Nailing 1/23/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/10/2025 Approved RYAN SALAZAR
Final 7/10/2025 Corrections Issued RYAN SALAZAR
Green Building Final 7/10/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 7/10/2025 Approved RYAN SALAZAR
Final 8/21/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 8/21/2025 Approved RYAN SALAZAR