4746 N LEDGE AVE 91602
Certificate Information: 4746 N LEDGE AVE 91602
- Application / Permit
- 20014-20000-02733
- Plan Check / Job No.
- B20VN08701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2ND FLR ADDITION TO (E) SFD
- Permit Issued
- Issued on 10/31/2020
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/29/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/18/2020 | APPLICANT |
| Plan Check Approved | 10/28/2020 | MOHAMMAD ESMAILI |
| Issued | 10/31/2020 | APPLICANT |
| CofO in Progress | 3/19/2024 | JOHN COLEMAN |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
| CofO Issued | 8/6/2024 | RUBEN SALAS |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 8/11/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/14/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/23/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/19/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 3/31/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 3/31/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 3/31/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | DANIEL DREW |
| Green Building Rough | 4/12/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 4/12/2021 | Approved | DANIEL DREW |
| Insulation | 4/19/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 4/23/2021 | Partial Approval | DAVID MATSON |
| Shower Pan | 5/17/2021 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 5/21/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/28/2021 | Approved | DANIEL DREW |
| Final | 7/28/2021 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 7/28/2021 | Approved | DANIEL DREW |
| Green Building Final | 7/28/2021 | Approved | DANIEL DREW |
| HVAC-Final | 7/28/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 7/28/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 7/28/2021 | Approved | DANIEL DREW |
| Final | 3/19/2024 | OK to Issue CofO | JOHN COLEMAN |