13379 W PIERCE ST 91331

Certificate Information: 13379 W PIERCE ST 91331

Application / Permit
20014-20000-02728
Plan Check / Job No.
B20VN08672
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRR SHAPED TWO BEDRMS & BATHRM ADDITION (39'1"X16'6") AT REAR & CONVERT EX BEDRM INTO FAMILY RM. ALL WORK PER WFPP.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 12/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/13/2020 HAYATO TSUCHIYA
Corrections Issued 7/14/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/2/2020 HAYATO TSUCHIYA
Plan Check Approved 11/24/2020 HAYATO TSUCHIYA
Issued 11/24/2020 APPLICANT
CofO in Progress 3/24/2021 MICHEL ABAJAN
CofO Issued 12/14/2021 MICHAEL SMITH
Permit Finaled 12/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/30/2020 ADRIAN CASTRO
Sewer availability Cleared 7/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/21/2020 ADRIAN CASTRO
ZI Cleared 9/21/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2020 Approved MICHEL ABAJAN
METHANE-Barrier 12/11/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 12/11/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/28/2020 Partial Approval MICHEL ABAJAN
METHANE-Rough 12/28/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 12/28/2020 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 1/27/2021 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 2/12/2021 Approved MICHEL ABAJAN
HVAC-Rough 2/12/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 2/12/2021 Approved MICHEL ABAJAN
Shower Pan 2/12/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/17/2021 Approved MICHEL ABAJAN
Green Building Rough 2/17/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/17/2021 Approved MICHEL ABAJAN
Insulation 2/22/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/22/2021 Approved MICHEL ABAJAN
Drywall Nailing 3/4/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/24/2021 Approved MICHEL ABAJAN
Final 3/24/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/24/2021 Approved MICHEL ABAJAN
HVAC-Final 3/24/2021 Approved MICHEL ABAJAN
PLUMBING-Final 3/24/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/24/2021 Approved MICHEL ABAJAN