5724 N ALLOTT AVE 91401

Certificate Information: 5724 N ALLOTT AVE 91401

Application / Permit
20014-20000-02715
Plan Check / Job No.
B20VN08635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE (18'2"X20'2") INTO ACCESSORY DWELLING UNIT W/ ADDITION (15'6"X14'). SEE COMMENTS
Permit Issued
Issued on 8/31/2020
Issuing Office
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 HAYATO TSUCHIYA
Corrections Issued 7/3/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 7/23/2020 HAYATO TSUCHIYA
Plan Check Approved 8/17/2020 HAYATO TSUCHIYA
Issued 8/31/2020 APPLICANT
CofO in Progress 11/5/2021 MICHAEL TEMPLE
Permit Finaled 4/15/2023 DANIEL ORRANTE
CofO Issued 4/15/2023 DANIEL ORRANTE
Permit Finaled 4/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/21/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/21/2020 ADRIAN CASTRO
Sewer availability Cleared 7/21/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 10/15/2020 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 10/15/2020 Not Ready for Inspection WILLIAM KUEHN
Underground Mechanical 10/15/2020 Partial Inspection WILLIAM KUEHN
Sewer 10/23/2020 Approved MATTHEW NELSON
Underground Mechanical 10/23/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 11/2/2020 Approved WILLIAM KUEHN
ELECTRICAL-Rough 11/2/2020 Approved WILLIAM KUEHN
Green Building Rough 11/2/2020 Not Ready for Inspection WILLIAM KUEHN
HVAC-Rough 11/2/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 11/2/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved WILLIAM KUEHN
Wood Frame 11/2/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 11/24/2020 Approved JENNIFER RABUCHIN
Green Building Rough 11/24/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/24/2020 Partial Approval JENNIFER RABUCHIN
Insulation 12/2/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 12/15/2020 Approved DAVID MATSON
Final 10/12/2021 Corrections Issued RICHARD DOCKUS
Green Building Final 10/12/2021 Approved RICHARD DOCKUS
PLUMBING-Final 10/12/2021 Corrections Issued RICHARD DOCKUS
Smoke Detectors 10/12/2021 Approved RICHARD DOCKUS
Final 10/29/2021 Not Ready for Inspection RICHARD DOCKUS
Final 11/4/2021 OK to Issue CofO RICHARD DOCKUS
ELECTRICAL-Final 11/19/2021 Approved RICHARD DOCKUS