17508-17510 W BLACKHAWK ST 91344

Certificate Information: 17508-17510 W BLACKHAWK ST 91344

Application / Permit
20014-20000-02693
Plan Check / Job No.
B20VN08602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 3'-0" X 3'-0" PORTION OF GARAGE TO HALLWAY, 18'-2" X 22'-4" ADDITION FOR NEW FAMILY ROOM AND BATHROOM W/ BAR SINK AND STORAGE ABOVE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 JEROME MAGAT PALMA
Corrections Issued 7/2/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 8/18/2020 JENNIFER LEE
Plan Check Approved 10/3/2020 JEROME MAGAT PALMA
Issued 10/26/2020 APPLICANT
CofO in Progress 6/29/2021 JEFFREY PARD
Permit Finaled 6/29/2021 JOHN JANSON
CofO Issued 6/29/2021 JOHN JANSON
Permit Finaled 6/29/2021 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 7/21/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/22/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/5/2021 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 2/8/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 2/10/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Approved JEFFREY PARD
Pre-Inspection 3/12/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 3/17/2021 Approved JEFFREY PARD
PLUMBING-Rough 3/17/2021 Approved JEFFREY PARD
Deputy Wood Construction 3/18/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/19/2021 Approved JEFFREY PARD
Green Building Rough 3/19/2021 Not Ready for Inspection JEFFREY PARD
Insulation 3/22/2021 Approved JEFFREY PARD
Drywall Nailing 3/31/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 3/31/2021 Approved JEFFREY PARD
Sewer 6/3/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 6/16/2021 Approved JEFFREY PARD
Final 6/16/2021 Corrections Issued JEFFREY PARD
Green Building Final 6/16/2021 Approved JEFFREY PARD
Green Building Rough 6/16/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 6/16/2021 Approved JEFFREY PARD
Final 6/28/2021 OK to Issue CofO JEFFREY PARD