8334 N HATILLO AVE 91306

Certificate Information: 8334 N HATILLO AVE 91306

Application / Permit
20014-20000-02668
Plan Check / Job No.
B20VN08545
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 10'-4" X 20'-9" TO EXTEND AND REMODEL (E) KITCHEN/LAUNDRY ROOM TO (E) 1-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/22/2020
Issuing Office
Current Status
CofO Issued on 5/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 JENNIFER LEE
Corrections Issued 7/2/2020 JENNIFER LEE
Plan Check Approved 8/4/2020 SERGIO MUNIZ
Issued 8/22/2020 APPLICANT
CofO in Progress 4/30/2021 JEFFREY PARD
Permit Finaled 5/3/2021 JOHN JANSON
CofO Issued 5/3/2021 JOHN JANSON
Permit Finaled 5/3/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/21/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/21/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/28/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 9/2/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 9/18/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 10/2/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 10/2/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 11/13/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 11/13/2020 Approved JEFFREY PARD
Green Building Rough 11/13/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 11/13/2020 Approved JEFFREY PARD
Wood Frame 11/13/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Approved JEFFREY PARD
Insulation 11/19/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 11/19/2020 Approved JEFFREY PARD
Drywall Nailing 12/3/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Approved JEFFREY PARD
Green Building Rough 12/3/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 12/3/2020 Approved JEFFREY PARD
Final 3/30/2021 Corrections Issued JEFFREY PARD
Green Building Final 3/30/2021 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/30/2021 Approved JEFFREY PARD
Final 4/15/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 4/15/2021 Approved JEFFREY PARD