4545 N BALBOA AVE 91316

Certificate Information: 4545 N BALBOA AVE 91316

Application / Permit
20014-20000-02667
Plan Check / Job No.
B20VN08544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND STORY ADDITIONS AND MAJOR REMODEL TO (E) SFD & ADD NEW ATTACHED GARAGE AND NEW ROOF. NEW OVERALL BUILDING DIMENSION: 48'7"X 81'2" NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 5/4/2021
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 MARVEL DELACRUZ
Corrections Issued 7/29/2020 MARVEL DELACRUZ
Quality Review Completed 7/31/2020 STEVEN KIM
Building Plans Picked Up 8/5/2020 APPLICANT
Applicant returned to address corrections 10/8/2020 MARVEL DELACRUZ
Applicant returned to address corrections 11/9/2020 MARVEL DELACRUZ
Applicant returned to address corrections 2/11/2021 MARVEL DELACRUZ
Plan Check Approved 3/5/2021 MARVEL DELACRUZ
Issued 5/4/2021 APPLICANT
CofO in Progress 1/9/2023 VINCENT HANLEY
Permit Finaled 2/4/2023 MICHAEL SMITH
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/2/2020 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 9/2/2020 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 9/2/2020 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 9/2/2020 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 9/2/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/3/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 10/8/2020 MARVEL DELACRUZ
Green Code Cleared 10/8/2020 MARVEL DELACRUZ
Distance to fire station Cleared 11/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/12/2020 MITESH PATEL
Hydrant and Access approval Cleared 11/19/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 11/24/2020 ADRIAN CASTRO
GPI Written Notices Cleared 12/1/2020 MARVEL DELACRUZ
Private sewage disp. approval Cleared 12/11/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/11/2021 Corrections Issued RONALD COWAN
Structural Steel Frame 5/13/2021 Partial Approval RONALD COWAN
Underground Mechanical 5/13/2021 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/21/2021 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 5/21/2021 Corrections Issued RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval RONALD COWAN
Footing/Foundation/Slab 6/24/2021 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Rough 12/7/2021 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 12/7/2021 Partial Inspection DAVID SANDOVAL
Deputy Wood Construction 12/27/2021 Approved VINCENT HANLEY
Deputy Wood Construction 12/28/2021 Conditional Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 2/28/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 5/5/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 5/5/2022 Approved DAVID SANDOVAL
HVAC-Rough 5/5/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 5/5/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/3/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Approved VINCENT HANLEY
Green Building Rough 6/3/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/3/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 6/3/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/17/2022 Partial Approval MORRIS JACKSON
Shower Pan 6/17/2022 Approved MORRIS JACKSON
Insulation 6/30/2022 Approved VINCENT HANLEY
Drywall Nailing 7/7/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/13/2022 Approved VINCENT HANLEY
Final 11/9/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 11/9/2022 Approved VINCENT HANLEY
Green Building Final 11/9/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 11/9/2022 Approved VINCENT HANLEY
Final 12/21/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved VINCENT HANLEY
Final 1/9/2023 OK to Issue CofO VINCENT HANLEY