4545 N BALBOA AVE 91316
Certificate Information: 4545 N BALBOA AVE 91316
- Application / Permit
- 20014-20000-02667
- Plan Check / Job No.
- B20VN08544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITIONS AND MAJOR REMODEL TO (E) SFD & ADD NEW ATTACHED GARAGE AND NEW ROOF. NEW OVERALL BUILDING DIMENSION: 48'7"X 81'2" NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/29/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 7/31/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/5/2020 | APPLICANT |
| Applicant returned to address corrections | 10/8/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 11/9/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/11/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 3/5/2021 | MARVEL DELACRUZ |
| Issued | 5/4/2021 | APPLICANT |
| CofO in Progress | 1/9/2023 | VINCENT HANLEY |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/2/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 9/2/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 9/2/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 9/2/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 9/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 10/8/2020 | MARVEL DELACRUZ |
| Green Code | Cleared | 10/8/2020 | MARVEL DELACRUZ |
| Distance to fire station | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/12/2020 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 11/19/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 12/1/2020 | MARVEL DELACRUZ |
| Private sewage disp. approval | Cleared | 12/11/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Corrections Issued | RONALD COWAN |
| Structural Steel Frame | 5/13/2021 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 5/13/2021 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 5/21/2021 | Corrections Issued | RONALD COWAN |
| Footing/Foundation/Slab | 5/21/2021 | Corrections Issued | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 6/24/2021 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/7/2021 | Partial Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 12/7/2021 | Partial Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 12/27/2021 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 12/28/2021 | Conditional Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 2/28/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/5/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/5/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/5/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 5/5/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/3/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/17/2022 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 6/17/2022 | Approved | MORRIS JACKSON |
| Insulation | 6/30/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/7/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/13/2022 | Approved | VINCENT HANLEY |
| Final | 11/9/2022 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/9/2022 | Approved | VINCENT HANLEY |
| Green Building Final | 11/9/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 11/9/2022 | Approved | VINCENT HANLEY |
| Final | 12/21/2022 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | VINCENT HANLEY |
| Final | 1/9/2023 | OK to Issue CofO | VINCENT HANLEY |